what is schedule variance and give the formula

Answers were Sorted based on User's Feedback



what is schedule variance and give the formula..

Answer / varun

percentage of time taken to complete the task

schedule variance== (actual duration-planned
duration)/planned duration * 100


as per my knowledge this is answer

Is This Answer Correct ?    97 Yes 50 No

what is schedule variance and give the formula..

Answer / ravi

Schedule Variance= Earned Vlaue - Planned Value
Earned Value-> Budget value of the work completed in
specified time
Planned Value -> Budget value of the work that was planned
to be completed in specific time
The difference reflects the amount of budget that could not
be completed or that was excessively done in specific time.

Is This Answer Correct ?    49 Yes 13 No

what is schedule variance and give the formula..

Answer / kt karthikeyan

Schedule Variance = (Actual Completion Date – Planned
Completion Date)/(Planned Completion date – Planned Start
Date + 1) * 100

Is This Answer Correct ?    57 Yes 27 No

what is schedule variance and give the formula..

Answer / hannah

SV = [(Actual End Date - Planned End Date)/(Planned End
Date - Planned start Date)]*100

Is This Answer Correct ?    31 Yes 12 No

what is schedule variance and give the formula..

Answer / manju

Scheule Variance = [(Actual Calendar Days - Planned
Calendar Days)/Planned Calendar Days]*100

Is This Answer Correct ?    16 Yes 12 No

what is schedule variance and give the formula..

Answer / tamil

Schedule Variance.

First find out the Delay(AED(Actual END Date)-PED(Planned
END Date)). Formula for this:

=IF(Actual Finish date="",0,IF(Actual Finish Date = Planned
Finish Date,0,IF(Actual Finish Date>Planned Finish
Date,NETWORKDAYS(Actual Finish,Planned Finish)-1,NETWORKDAYS
(Actual Finish,Planned Finish))))).

And then Find out the Actual Schedule(PED(Planned End Date)-
PSD(Planned Start Date)). Formula for this:
NETWORKDAYS(Planned Finish date,Planned Start Date)

And then Finally Schedule Variance Formula Is:

IF(NOT(Actual Schedule=0),(Actual Schedule/Delay%),0)

Please check it....

Is This Answer Correct ?    7 Yes 3 No

what is schedule variance and give the formula..

Answer / manas

There is difference between schedule variance and schedule slippage.
Schedule slippage- Schedule slippage is key performance indicator that shows amount of time the project is delayed (expressed in %) compared to its baseline start and Finish dates.
Formula for computation of schedule slippage: - (Actual Project Duration – Planned Project Duration / Planned Project Duration) * 100
Formula for compute Actual Project Duration: - (Project Actual End Date – Project Actual Start Date)
Formula for compute Planned Project Duration or baseline duration: - (Project Planned End Date – Project Planned Start Date)

Schedule Slippage metrics helps in identifying the problems of previous projects and making more realistic predictions for future projects

Schedule Variance- 
Schedule Variance term is used in EVM which states how much cost of work is yet to be completed as per schedule.
SV- BCWP-BCWS.

Is This Answer Correct ?    3 Yes 0 No

what is schedule variance and give the formula..

Answer / harsh

These answers looks unrealistic. If we want to calculate SV
and EV during the project, how it can be calculated then.

SAP uses concept of POC (Percentage of completion)to
calculate EV & SV

SV - (Scheduled Effort - Burnt Effort)/ Scheduled Effort

Definition -
Scheduled Efforts (BCWS) = Estimated POC * Estimated Effort
Burnt efforts(BCWP)= Actual POC X Estimated Effort
Estimated POC = (Current Date - Planned Start Date)/ Total
Planned Duration
Actual POC = (Total planned efforts for project - total
spent efforts(Present state))/ Total Planned efforts for
project.

Is This Answer Correct ?    2 Yes 0 No

what is schedule variance and give the formula..

Answer / g.vijayan(annamalai university

schedule variance=(actual duration-planned
duration)/planned duration*100

Is This Answer Correct ?    2 Yes 0 No

what is schedule variance and give the formula..

Answer / sushilkumar pandey

SV = (Actual-Estimated)*100/Estimated

If
Estimated Duration= 43 Days
Actual Duration = 45 Days

Then

SV = (45-43)*100/43

SV = 200/43

SV = 4.65

Is This Answer Correct ?    7 Yes 6 No

Post New Answer

More Manual Testing Interview Questions

Your manager has taken you onboard as a test lead for testing a web-based application. He wants to know what risks you would include in the Test plan. Explain each risk factor that would be a part of your test plan

1 Answers   Crea,


i have 2 text boxes first is you have to enter the name of person(enter first name and last name) and second is enter the company name and below there is a submit button when i enter first name and last name and the company name it displays his linkedIN account that is name of the person and company details he is working can you tell me test case for this ? i will give the sketch of this question first name last name company 1 2 3 4 submit

1 Answers  


what is prototyping model,RAD model V model, spiral model?????

0 Answers  


in this project how many modules?

2 Answers   Wipro,


What are the qualities if the tester ?

9 Answers   Infosys,






Difference between Stakeholder and Relevant Stakeholder?

0 Answers   Midas Technologies,


test cases on bangles???

0 Answers  


hi friends, anybody WHO NEEDS PROPER GUIDANCE TO MAKE CARRER IN TESTING PLS CONSULT ME. U WILL DEFINITELY BE BENEFITTED. My EMAIL ID: sun2k8@rediffmail.com Test Lead (IBM)

11 Answers  


What is the difference between stress, volume and load testing?

7 Answers  


Explain crud testing.

0 Answers  


If planned effort and actual effort is same, then how to calculate the effort variance ??

1 Answers   Accenture,


What are the containts of usecase document?

1 Answers  


Categories