Answer Posted / manas
There is difference between schedule variance and schedule slippage.
Schedule slippage- Schedule slippage is key performance indicator that shows amount of time the project is delayed (expressed in %) compared to its baseline start and Finish dates.
Formula for computation of schedule slippage: - (Actual Project Duration – Planned Project Duration / Planned Project Duration) * 100
Formula for compute Actual Project Duration: - (Project Actual End Date – Project Actual Start Date)
Formula for compute Planned Project Duration or baseline duration: - (Project Planned End Date – Project Planned Start Date)
Schedule Slippage metrics helps in identifying the problems of previous projects and making more realistic predictions for future projects
Schedule Variance-
Schedule Variance term is used in EVM which states how much cost of work is yet to be completed as per schedule.
SV- BCWP-BCWS.
| Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
How to overcome pesticide paradox?
What is Bomb Testing?
what is agile model and spiral maodel?pls explain with an example?
few automation basic questions One question to write a scriot in any language you know.
what we have to read to gain knowledge in banking and financial domain(software testing) for 4+ experience
Can anyone please suggest me a online book on manual testing??
What is an audit report? Whom is it done by?
1.How to maintain the Bug status Report? 2.What is project based Company and product based company?
What is the main use of preparing traceability matrix and explain the real time usage?
Could anyone share FAQs for Test Manager position...
What’s the difference between verification and validation in testing?
How do u determine,what to be tested?
1. what is baseline document , can you say any two ?
how many modules in ur bank project? what functionalities r there?how did u check? could u plz expalin ur banking project?
Can test condition,testcase and testscript help u in performing the static testing