Answer Posted / varun
percentage of time taken to complete the task
schedule variance== (actual duration-planned
duration)/planned duration * 100
as per my knowledge this is answer
| Is This Answer Correct ? | 97 Yes | 50 No |
Post New Answer View All Answers
What is meant by Boundary value analisis and Equalence partitioning? Can give derive this using these methods? In a system designed to work out the tax to be paid: An employee has £4000 of salary tax free. The next £1500 is taxed at 10% The next £28000 is taxed at 22% Any further amount is taxed at 40% Which of these groups of numbers would fall into the same equivalence class? a) £4800; £14000; £28000 b) £5200; £5500; £28000 c) £28001; £32000; £35000 d) £5800; £28000; £32000
On login window for username and password auto populated field means what !
what is test case management?explain in brief.
There is an opening in our organization Sierra Atlantic, Hyderabad. All Manual test engineers with 2-3 years of experience can forward your resumes to mah_cs82@yahoo.com before May 01, 2008. (Only manual testers) with a covering letter, current CTC and Expected CTC.
If you are handling a product testing and if there are around 100 test cases and in them few test cases are failed then at the end of the day how will you treat whether the product is pass/fail.? consider the failed test cases are in functional requirements.
1.For a single module how many builds are possible 2.what will be the max or min time to finish up an single module
what is the impact analysis?
Explain Single View Testing ?
how to write the test cases for mark as read/unread mails for gmail inbox?and what are the testings we will do?
What does 100% statement coverage mean?
How a test engineer will convince a test lead when he didn't approve the bug as a report ???
I have 2 yrs 10 months experience in manual testing. there is a gap of 3 yrs in between. just 3 months before i rejoined the same company. I am looking for new & better job.What I have to enhance my career to up level, should I have to do Automation course or any other. Guide me properly.
i have source and target having same data structure 500 fields and one lacks records. how to validate data. write 5 scenarios.
can anyone tell me the questions that can be posed in an interview for a 5 year experienced person in manual testing
please give information about ERP Projects and how V-model use in project