Answer Posted / sushilkumar pandey
SV = (Actual-Estimated)*100/Estimated
If
Estimated Duration= 43 Days
Actual Duration = 45 Days
Then
SV = (45-43)*100/43
SV = 200/43
SV = 4.65
| Is This Answer Correct ? | 7 Yes | 6 No |
Post New Answer View All Answers
How the application is launched to the production environment?
I have 2+ year of work exp in manual testing and i have good knowledge in QTP.anybody have requirement in your company please please tell me
Hello testers I am an Bsc Hotel mgmt Degree holders but now am doin my software testin programme, side by MCA Master degree an have 6 months exp i testing in company.. i want to change my CV according IT based. so can anyone help me with sendin any sample CV of urs.. do me this favour it wil be very helpful for me prepare CV for interviews....
How will you set the Dependency in the Quality center? Say if you will fail a test case and two or more test cases are dependent on that particular test case. In this case how will you handle in failing the test case.
What is the difference between coupling and cohesion?
What are the main key components in Web applications and Client Server applications? and their differences?
write test condition for testing SMS service of a mobile phone maximun length is 100 character while sending and 80 character for receiving write test scenarios do not write test cases
what is sanity test (or) build test?
Can you explain equivalence partitioning?
What is Stability and Performance Testing in Testing the TV
What and why is api testing?
What are the properties of a good requirement?
test measurment techniques
Can you explain usability testing?
How to overcome pesticide paradox?