Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


You have accumulated project information throughout the project and need to distribute some important information you just received. All of the following are part of information distribution methods except;
A. Electronic mail
B. Videoconferencing
C. Electronic databases
D. Voice mail


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

You are the project manager for Heart of Texas casual clothing company. Your project involves installing a new human resources system. You've identified the risks associated with this project and are ready for the next step. What is the next step? A. You will evaluate the risks and assign probabilities and impacts using Qualitative and/or Quantitative Risk Analysis. B. You will use the Delphi technique to confirm the risks you've detailed and identify others you may have missed. C. You must evaluate the risks and assign probabilities and impacts using both Qualitative Risk Analysis, which comes first, then Quantitative Risk Analysis. D. You will define the steps to take to respond to the risks and detail them in the risk response plan.

0 Answers  


You do not expect the types of variances that have occurred on the project to date to continue. If BAC = 300, ETC = 275, PV= 300, AC = 200, EV = 250, and CPI = 1.25, what is the EAC? A. 240 B. 250 C. 475 D. 150

0 Answers  


You are project manager for an engineering company. Your company won the bid to add ramp-metering lights to several on-ramps along a stretch of highway at the south end of the city. You subcontracted a portion of the project to another company. The subcontractor's work involves digging the holes and setting the lamp poles in concrete. The subcontractor's performance is not meeting the contract requirements. All of the following are valid options except: A. You document the poor performance in written form and send the correspondence to the subcontractor change request through Contract Administration. B. You terminate the contract for poor performance and submit a change request through Contract Administration. C. You submit a change request through Contract Administration to ask the subcontractor to comply with the terms of the contract. D. You agree to meet with the subcontractor to see if a satisfactory solution can be reached.

0 Answers  


What are the Quality Planning process outputs? A. Quality management plan, bench marking, checklists, evaluation criteria B. Quality management plan, bench marking, operational definitions C. Quality management plan, checklists, inputs to other processes D. Quality management plan, operational definitions, checklists, inputs to other processes

0 Answers  


Which of the following tools and techniques shows the impacts of one decision over another as well as the probability and cost of each risk along a logical path? A. Simulation B. Decision tree C. Probability/impact risk matrix D. Sensitivity analysis

0 Answers  


Procurement audits review what? A. The procurement process from Procurement Planning through Contract Administration B. The contract administration process from Solicitation Planning through Contract Administration C. The procurement process from Procurement Planning through Contract Closeout D. The contract administration process from Solicitation Planning through Contract Closeout

0 Answers  


Describe the risk in software engineering.

0 Answers  


What is one of the advantages of a functional structure? A. All employees report to one manager and have a clear chain of command. B. All employees report to two or more managers, but project team members show loyalty to functional managers. C. The organization is focused on projects and project work. D. Teams are collocated.

0 Answers  


What is "Readjustig goal and Milestone" in project managment and project planing

16 Answers   IBM,


Which of the following is true regarding product descriptions? A. The product description is an output of the Initiation process. It describes the characteristics of the product or service. B. The product description is an output of the Initiation process. It describes the characteristics of the product or service and less detail in the early phases of the project. C. The product description is an input of the Initiation process. It describes the characteristics of the product or service and contains a lot of detail in the early phases of the project. D. The product description is an input of the Initiation process. It describes the characteristics of the product or service.

0 Answers  


You are a project manager for Dakota Software Consulting Services. You're working with a major retailer that offers their products through mail-order catalogs. They're interested in knowing customer characteristics, the amounts of first-time orders, and similar information. As a potential bidder for this project, you worked on the RFP response and submitted the proposal. When the selection committee received the RFP responses from all the vendors bidding on this project, they used a weighted system to make a selection. Which process did this occur in? A. Source Selection B. Solicitation C. Requisition D. Contract Administration

0 Answers  


The project charter: A. Includes a product description, describes the business need of the project, and is published by the project manager B. Includes a product description, describes the business need of the project, and is published by the project sponsor C. Includes the contract when the project is performed by a vendor and is published by a manager external to the project D. Includes a product description, describes the business need of the project, and is published by a manager external to the project

0 Answers  


Categories