you are the project manager of a project , customer is asking for a change in scope and agrees that it will be a CR. But you do not want to take the CR for whatever reason. How will you convince the customer in doing so
Answers were Sorted based on User's Feedback
Answer / girishrangaiah
I will have a meeting with the customer on this CR aspect
and explain him the importance of delevering the ongoing
approved commitments to him on time. Also will make him
understand the Time Constraint and non availability of
effective Resources for taking up the CR immediatly.
But would assure him that his CR will be given high
priority in the next phase after the existing commitments
are delivered.
| Is This Answer Correct ? | 39 Yes | 3 No |
Answer / rajeev a
Only giving the resource unavailability angle may not satisfy client, he will simply say that he is client and paying for the CR and you being a service provider should provide me what i ask...
So instead, analyse the CR completely from technical point of view along with the experts and then with delivery point of view. See what are the impacts on the existing features, quality.communicate those impacts first to the client in your client meeting..that might sound better to the client.
| Is This Answer Correct ? | 2 Yes | 0 No |
You are a project manager for Move It Now trucking company. Your company specializes in moving household goods across the city or across the country. Your project involves upgrading the nationwide computer network for the company. Your lead engineer has given you the following estimates for a critical path activity: 60 days most likely, 72 days pessimistic, 48 days optimistic. What is the expected value, or weighted average? A. 54 B. 66 C. 60 D. 30
You are the project manager for Fun Days vacation packages. Your new project assignment is to head up the Fun Days resort opening in Austin, Texas. You are estimating the duration of the project plan activities, devising the project schedule, and monitoring and controlling deviations from the schedule. Which of the Project Management Knowledge Areas are you working in? A. Project Scope B. Project Quality C. Project Integration D. Project Time
You have accumulated project information throughout the project and need to distribute some important information you just received. All of the following are part of information distribution methods except; A. Electronic mail B. Videoconferencing C. Electronic databases D. Voice mail
If your expected value is ll0 and the standard deviation is l2, which of the following is true? A. There is approximately a 99 percent chance of completing this activity between 86 and 134 days. B. There is approximately a 68 percent chance of completing this activity between 98 and 122 days. C. There is approximately a 95 percent chance of completing this activity between 98 and 122 days. D. There is approximately a 75 percent chance of completing this activity between 86 and 134 days.
You are ready to perform the Activity Sequencing process for your project. To make your job easier, you're going to use a software tool to help you draw a PDM network diagram. Most software programs use this technique. You know all of the following are true regarding the PDM except: A. It shows the activities on arrows and connects them to dependencies usually depicted as circles. B. It’s also called AON. C. It shows the activities in boxes with arrows connecting the dependent activities. D. It uses four types of dependency relationships of which finish to start is one.
All of the following are tools and techniques of the Integrated Change Control process except: A. Configuration management B. Performance measurements C. Change requests D. Additional planning
You've constructed the WBS for your recent project. Level two assignments have been made, and you've requested that the sub project manager’s report back to you in 3 weeks with each of their individual WBS constructed. All of the following are true except: A. The work package level facilitates resource assignments. B. The work package level is the lowest level in the WBS. C. The work package level defines the agreed-upon deliverables. D. The work package level facilitates cost and time estimates. ?
Project managers have the highest level of authority and the most power in which type of organizational structure? A. Projectized B. Strong matrix C. Functional D. Balanced matrix
You are a project manager for Pizza Direct, which is a retail pizza delivery store. Your company is competing with another retail store for the option of opening two new stores in a foreign country. You've been told that it is culturally unacceptable to eat certain foods in this country. You know that one of these foods happens to be a secret ingredient in the pizza sauce. What is the most appropriate response? A. Inform the potential partners that your sauce recipe is secret, but you’re certain there are no forbidden ingredients in it. B. Inform the potential partners that you suspect there might be a forbidden ingredient in the sauce and you'll request an investigation to determine if any of them exist in the sauce. C. Inform the potential partners that a forbidden ingredient exists in the sauce and determine to work with them to come up with another ingredient to replace that one. D. Don't tell the potential partners about the ingredient because the sauce they'll be using in the stores is shipped to them already prepared in cans. They won't know the ingredient is in the sauce.
You are a project manager for Candy Works candy factory. Your project involves reporting information from the newly installed candy-counting machine to the financial system. This will give executives the ability to see production run counts at any rime during the day. The project sponsor has promised you a bonus if you get this project completed two weeks sooner than the scheduled project end date. The bonus will come in handy on your trip to the Bahamas planned for later this spring. You've got a few remaining project activities to wrap up before you can close out the project. Which of the following is the most appropriate response? A. You tell the sponsor the project is complete and treat the remaining activities as though they're problems that came up after project closure so that you can still get the bonus. B. You tell the sponsor the remaining activities are outside the scope of the project so the project really is completed and collect your bonus. C. You tell the sponsor the stakeholders added these requirements after the project was well under way and you never agreed to include them in the project so the project really is complete, and you collect your bonus. D. You tell the sponsor you aren't going to make the two-week early completion date as there are remaining activities to finish up.
You are going to take some performance measurements for your current project. You know that PV = 450, AC = 500, and EV = 375. What is the CV and SV respectively? A. CV = 125, and SV = 75 B. CV=-75, and SV=-125 C. CV = 75, and SV = 125 D. CV=-125, and SV=-75
You are a project manager working on a new software product. Your company plans to market to businesses. The project sponsor told you that the project must be completed by September 1. The company plans to demo the new software product at a trade show in late September and therefore needs the project completed in time for the trade show. However, the sponsor has also told you that the budget is fixed at $85,000 and cannot be increased by even $10 due to overall budget cuts this year. You must complete the project within the given time frame and budget. Which of the following is the primary constraint for this project? A. Budget B. Quality C. Time D. Schedule