The VP of marketing approaches you and requests that you change the visitor logon screen on the company’s website to include a username with at least six characters. This is considered:
A. Project initiation
B. Ongoing operations
C. A project
D. Project execution
Answer / hafiz muhammad zeeshan
B. Ongoing operations
Explanation: Projects exist to create a unique product or service. The logon screen in this question is not a unique product. A minor change has been requested, indicating this is an ongoing operation function. Some of the criteria for projects are that they are unique, temporary with definitive start and end dates, and considered complete when the project goals are achieved.
| Is This Answer Correct ? | 0 Yes | 1 No |
What are the 10 knowledge areas of project management?
How do you set goals for your team?
The Project Human Resource Management knowledge area contains which of the following processes? A. Staff Acquisition, Team Development, and Resource Planning B. Staff Acquisition, Team Development, and Performance Reporting C. Organizational Planning, Staff Acquisition, and Team Development D. Organization Planning, Team Development, and Resource Planning
Your project selection committee used a weighted scoring model and found that Project B, with a score of 54, should be chosen over the other competing projects. Which of the following is true? A. Weighted scoring models are a benefit measurement method, which is a tool and technique in the Initiation process. B. Weighted scoring models are a constrained optimization method, which is an output of the Initiation process. C. Weighted scoring models are a constrained optimization method, which is a tool and technique in the Initiation process. D. Weighted scoring models are a benefit measurement method, which is an output of the Initiation process.
You are the project manager for a web development project. You hold regular project status meetings and publish status reports on a timely basis. You know that communication is one of your most important functions. As such, all of the following are true except: A. Senders are responsible for sending clear, concise, complete messages. B. Receivers are responsible for understanding the message. C. Communication can be vertical or horizontal or both. D. Effective communication techniques include making eye contact, nodding, and asking clarifying questions.
All of the following are tools and techniques of the Quality Control process except: A. Monte Carlo Analysis B. Statistical sampling C. Pareto diagrams D. Trend analysis
You are a project manager for Penguin Software. Your company creates custom software programs for hospitals and large dental offices. You have just completed a project and are performing earned value analysis, trend analysis, and performance reviews. Which of the following is true? A. This is performance measurement documentation, which is an input to the Contract Closeout process B. This is performance measurement documentation, which is an input to the Administrative Closure process C. These are performance reporting tools and techniques of the Administrative Closure process D. These are performance reporting tools and techniques of the Contract Closeout process
How does a project manager can avoid the above given ten points for the success of project.
Your nonprofit organization is preparing to host its first annual 5K run/walk in City Park. You worked on a similar project for the organization two years ago when it co-hosted the 10K run through Overland Pass. Which of the Initiation process inputs might be helpful to you on your new project? A. The strategic plan, because you'll want to make sure the project reflects the overall strategic direction of the organization. B. Historical information on the 10K run project. You might be able to gather helpful project information since this new project is similar in nature. C. The product description, which would describe all the details of the run/walk program. D. Historical information from the recent blood drive project.
What are the different types of software risks?
You are a project manager responsible for the construction of a new office complex. You are taking over for a project manager who recently left the company. The prior project manager completed the project charter and the scope statement for this project. In your interviews with some key stakeholders, you conclude that the scope statement was poorly constructed. You know all of the following are true except: A. It will be difficult to assess future project decisions from this scope statement. B. It will be difficult to decompose the deliverables from this scope statement. C. It will be difficult to assess cost and time estimates from this scope statement. D. It will be difficult to create an accurate WBS from this scope statement.
What do you think you can bring to this position?
0 Answers Ross Stores, Starbucks,