The VP of marketing approaches you and requests that you change the visitor logon screen on the company’s website to include a username with at least six characters. This is considered:
A. Project initiation
B. Ongoing operations
C. A project
D. Project execution
Answer / hafiz muhammad zeeshan
B. Ongoing operations
Explanation: Projects exist to create a unique product or service. The logon screen in this question is not a unique product. A minor change has been requested, indicating this is an ongoing operation function. Some of the criteria for projects are that they are unique, temporary with definitive start and end dates, and considered complete when the project goals are achieved.
| Is This Answer Correct ? | 0 Yes | 1 No |
You’re promised your team two days of paid time off plus a week’s training in the latest technology of their choice if they complete their project ahead of schedule. This is an example of which of the following? A. Achievement theory B. Expectancy theory C. Maslow's theory D. Contingency theory
The project manager has the greatest influence over quality during which process? A. Quality Planning B. Quality Assurance C. Quality Control D. Quality Change Control
What is the name of the unplanned response used to deal with negative risk events in the Risk Monitoring and Control process? A. Mitigation B. Contingency plans C. Workarounds D. Corrective action
What are the inputs to the Initiation process? A. Product description, strategic plan, project selection criteria, and historical information B. Product description, strategic plan, project overview document, and historical information C. Strategic plan, project overview document, feasibility study, and historical information D. Product description, strategic plan, constraints, and assumptions
What are the initiation process outputs? A. Project charter, identification and assignment of project manager, constraints, and project overview documents B. Project charter, project overview, feasibility study, and constraints C. Project charter, identification and assignment of project manager, constraints, and assumptions D. Identification and assignment of project manager, project overview, constraints, and assumptions
What are the triple constraints? A. Time, schedules, and quality B. Time, availability, and quality C. Time, money, and schedules D. Time, money, and quality
You are a project manager for Move It Now trucking company. Your company specializes in moving household goods across the city or across the country. Your project involves upgrading the nationwide computer network for the company. Your lead engineer has given you the following estimates for a critical path activity: 60 days most likely, 72 days pessimistic, 48 days optimistic. What is the standard deviation? A. 22 B. 20 C. 2 D. 4
A project is considered successful when: A. The product of the project has been manufactured. B. The project sponsor announces the completion of the project. C. The product of the project is turned over to the operations area to handle the ongoing aspects of the project. D. The project meets or exceeds the expectations of the stakeholders.
Your project was just completed. Due to some unfortunate circumstances, the project was delayed causing cost overruns at the end of the project. Which of the following is true? A. You document the circumstances as lessons learned. B. You pay particular attention to archiving the financial records for this project. C. Your project ended due to starvation because of the cost overruns. D. You document the circumstances surrounding the project completion during the Scope Verification process.
Your hardware vendor left you voicemail saying that a snowstorm in the Midwest will prevent your equipment from arriving on time. You identified a risk response for this risk and have arranged for a local company to lease you the needed equipment until yours arrives. This is an example of which risk response strategy? A. Transference B. Acceptance C. Mitigation D. Avoidance
Your organization regularly uses a tool and technique of the Contract Closeout process to identify lessons learned, including the successes and failures, which will benefit future activity on this project and on future projects. Which tool and technique arc they using? A. Product documentation inspection B. Contract process review C. Performance measurement review D. Procurement audit
During the opening rounds of contract negotiation, the other party uses a fait accompli lactic. Which of the following is true? A. One party agrees to accept the offer of the other party but secretly knows they will bring the issue hack up at a later time. B. One party claims the issue under discussion was documented and accepted as part of Scope Verification. C. One party claims the issue under discussion has already been decided and can't be changed. D. One party claims to accept the offer of the other party provided a contract change request is submitted describing the offer in detail.