You are a project manager for Pizza Direct, which is a retail pizza delivery store.
Your company is competing with another retail store for the option of opening two new stores in a foreign country. You have been invited to dinner with the prospective foreign business partners and their spouses upon your arrival. You know that all of the following are generally true except:
A. You should spend time building relationships with your prospective foreign business partners before getting down to business.
B. You should explain your company's rules, standards, and operating policies at your first meeting with the prospective foreign business partners.
C. You should build an atmosphere of mutual trust and cooperation.
D. You should respect the cultural differences you'll encounter when working with your prospective foreign business partners.
Answer / Avatar Kumar
C. You should build an atmosphere of mutual trust and cooperation.
| Is This Answer Correct ? | 0 Yes | 0 No |
The Critical Path Method is a mathematical tool and technique of the Schedule Development process. All of the following are true regarding CPM except: A. Determines a single early and late start date and a single early and late finish date B. Calculates expected value C. Focuses on the calculation of float time D. Shows the critical path, or the path with the longest duration
What is raid in project management?
Contract documentation is an input to the Contract Closeout process. Contract documentation might include all of the following except: A. Supporting documents B. Contract changes C. Financial documents D. Procurement audit documents
You are developing your project schedule and have decided to use the PERT method to determine project duration. The estimates you've gathered so far include the following: Most likely is 200 hours, optimistic is 180 hours, and pessimistic is 220 hours. Which of the following is the correct PERT estimate? A. 190 B. 266 C. 200 D. 210
You are the project manager for Design Your Web Site, Inc. Your company is designing the website for a national grocery store chain. You have your activity list in hand and several time estimates and are ready to diagram the activity dependencies. You should use which of the following? A. PDM techniques B. PDM or ADM techniques C. AON techniques D. ADM techniques
You are the project manager for Lucky Stars Candies. You've identified the deliverables and requirements and documented them where? A. In the scope statement, which will be used as in input to the Scope Definition process B. In the scope definition document, which is used as an input to the Scope Planning process C. In the WBS, which is an output of the Scope Planning process D. In the WBS, which is a tool and technique of the Scope Definition process
How do you motivate team members?
What is the purpose of the project charter? A. To recognize and acknowledge the project sponsor B. To recognize and acknowledge the existence of the project and commit organizational resources to the project C. To acknowledge the existence of the project team, project manager, and project sponsor D. To describe the selection methods used to choose this project over its competitors
You are ready to perform the Activity Sequencing process for your project. To make your job easier, you're going to use a software tool to help you draw a PDM network diagram. Most software programs use this technique. You know all of the following are true regarding the PDM except: A. It shows the activities on arrows and connects them to dependencies usually depicted as circles. B. It’s also called AON. C. It shows the activities in boxes with arrows connecting the dependent activities. D. It uses four types of dependency relationships of which finish to start is one.
Your nonprofit organization is preparing to host its first annual 5K run/walk in City Park. You worked on a similar project for the organization two years ago when it co-hosted the 10K run through Overland Pass. Which of the Initiation process inputs might be helpful to you on your new project? A. The strategic plan, because you'll want to make sure the project reflects the overall strategic direction of the organization. B. Historical information on the 10K run project. You might be able to gather helpful project information since this new project is similar in nature. C. The product description, which would describe all the details of the run/walk program. D. Historical information from the recent blood drive project.
The Project Management Knowledge Areas: A. Include Initiation, Planning, Executing, Controlling, and Closing B. Consist of nine different areas that bring together processes that have things in common C. Consist of five different processes that bring together phases of projects that have things in common D. Include Planning, Executing, and Controlling processes as these three processes are commonly interlinked
You are a contract project manager working with the State of Bliss. Your latest project involves rewriting the Department of Revenue's income tax system. One of the key stakeholders is a huge movie huff, and she has the power to promote you into a better position at the conclusion of this project. She's discovered that one of her favorite superstars lives in the State of Bliss and therefore must file income tax star. What is the most appropriate response? A. Report her to the management team B. Refuse to comply with the request, citing conflict of interest and violation of confidential company data C. Look up the information she's requested. Since the data is considered part of the project, there is no conflict of interest D. You believe that tax records are public information, so you comply with the request