Answer / vishnutom
960 Number of bricks are required.
Explanation:
100 Sqft area of 5" wide
as the brick size is given in inches, convert the area in to
inches from sq.ft.
1 ft = 12 inches
1 sq.ft=12^2 sq.inches ie.,= 144 sq.inches
100 sq.ft = 100*144= 14400 sq.inches.
Length of brick = 9"
Width of brick= 5"
Thickness of brick= 3"
but in question it was given that the 100 sqft area of 5"
wide only..
Hence keeping 5" wide side of brick in position of 5" wide
area, Length of area 14400 sq.inches= (LxB=Area)
(L)*5"=14400.
L=14400/5=>2880 inches
No. of bricks= 2880/ht of each brick
Answer:
=> If we keep 3" side of brick along length the bricks
required should be 2880/3=>960 No. of bricks
=> If we keep 9" side of brick along length the bricks
required should be 2880/9=>320 No. of bricks
Check:
1) 320*9"*5"=14400Sq.inches=> 100 Sq.ft
2) 960*3"*5"=14400Sq.inches=> 100 Sq.ft
| Is This Answer Correct ? | 8 Yes | 4 No |
Answer / sandip santra
there should be required of 417nos bricks.
| Is This Answer Correct ? | 8 Yes | 5 No |
Answer / srikanth
100/10.76=9.29sq.mt
.25x.75=0.187
10.76/0.187=57.5
57.5x9.29=534.54 no.s of bricks
| Is This Answer Correct ? | 0 Yes | 1 No |
how to find out compressive strength of concrete
what is the procedure of plastering..?
I've one slab of 24m x 43m. How to calculate required steel For this slab.
1)What is Suggested type of cement for concreting at water, for mass concreting and where the chaces of gettin attucked by salt? 2)How many types of camber? 3)why we always preffer short column in case of residential building? 4) Is there any advantages between the use of One way slab & two way slab? 5)What shoul be the % of steel for R. C. C. perpose based on volume & area ?
how to caliculate required amount of cement and sand required for 1cu.m.
when we calculate concrete volume in footing the column along with footing up to the ground level is also taken or not ?
How to decide the Lap Length in Steel Reinforcement
which grade of concrete is the strongest? M20,M25,M30,M35 or M40?
what is total volume of ingredients used in concrete accordingly
I need model question papers for writing the Dubai municipality exam,for G+1
Why shoring is employed in building industry?
1 cubic meter contains how many bricks
47 Answers Guru Tech, Krati Enterprises, L&T,
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)