Waht is the level of criticallity in Project management for
a Project which is started in maintenance Phase ? Which
phase of Project management theory must be more focused for
such kind of projects .

Answers were Sorted based on User's Feedback



Waht is the level of criticallity in Project management for a Project which is started in maintena..

Answer / rsm

The level of criticality for a project which is started in
maintenance phase is medium as it has already gone thru' the
GO LIVE phase. And the phase of project management theory
that should be applied for projects in maintenance phase is
Monitoring and Controlling.

Is This Answer Correct ?    44 Yes 7 No

Waht is the level of criticallity in Project management for a Project which is started in maintena..

Answer / prabhu n d

- Project by definition should have verifiable output
(product) to be produced with in specified time frame.
Maintenance phase of a project should be treated like a
program with clear definition of scope of maintenance
activities and can go on for fixed period say in number of
years.
- The criticality of the project depends on the nature of
the product being supported i.e., if it is a mission
critical product (say online banking or share trading
systems etc.,) the criticality would be very high else it
could be between medium to low.
- Monitoring (Monitor the completion of tasks as per SLA)
- Controling (Duration and cost over runs on each tasks or
group of tasks)
- Scope Management ( Number of support requests / critical
nature requests allowed for the program duration )

Is This Answer Correct ?    29 Yes 2 No

Waht is the level of criticallity in Project management for a Project which is started in maintena..

Answer / srinivasa rao paidisetti

Any project is unique and one of its kind. Hence,
criticality would be at par with any other project.
Business weightage might change for a project in an
organisation based on various parameters like the
beneficiaries, cost, technical know-how etc.

For any project, Planning Phase is the Key. Execution
phase will be successful upon seamless Planning and careful
Monitoring & Controlling

Is This Answer Correct ?    6 Yes 2 No

Waht is the level of criticallity in Project management for a Project which is started in maintena..

Answer / vijay kumar allala

If the project is just started in maintenance phase or in
warranty period(a time period for which the support is
mandatory after GO-LIVE), the criticality is very high.This
is the period where most of the end-users will start using
the system. They might encounter different types of issues
which might not be an technical or functional issue, which
might be a perceived as Issue due to lact of knowledge.
These knowledge gaps must be addressed very quickly to
avoid further escalations and misconceptions about the
system.The Admin team and infrastructure team should be
extra cautious and should regularly check the statuses of
the different systems for their availability.

Is This Answer Correct ?    2 Yes 0 No

Waht is the level of criticallity in Project management for a Project which is started in maintena..

Answer / shri

Medium level of criticality.
Monitoring and control.

Is This Answer Correct ?    2 Yes 3 No

Waht is the level of criticallity in Project management for a Project which is started in maintena..

Answer / manish

Criticality is high, customer has to be satisfied in all
aspects of product. However being a overhead for project
management it has to be bind with SLA to have clear
resource utilization picture. Maintenance is important area
and can not be undermine - for organization to understand
the weak product areas, customer [sitting on contract
renewal) etc. Maintenance should not take new module
enhacement or new functionality development, this team not
meant for this.

More focus should be in analysis/ code phases with clsear
focus as below,

1. Analysis:- It should be impact analysis no new
functionality understanding etc.
2. Code: Mantra should be as less code lines change to fix
the defect

Is This Answer Correct ?    1 Yes 4 No

Post New Answer

More Project Management Interview Questions

You know that PV = 475, AC = 430, EV = 480, EAC = 40, and BAC = 525. What is VAC? A. 440 B. 390 C. 485 D. 435

0 Answers  


All of the following are tools and techniques of the Quality Control process except: A. Monte Carlo Analysis B. Statistical sampling C. Pareto diagrams D. Trend analysis

0 Answers  


What are the initiation process outputs? A. Project charter, identification and assignment of project manager, constraints, and project overview documents B. Project charter, project overview, feasibility study, and constraints C. Project charter, identification and assignment of project manager, constraints, and assumptions D. Identification and assignment of project manager, project overview, constraints, and assumptions

0 Answers  


If your expected value is ll0 and the standard deviation is l2, which of the following is true? A. There is approximately a 99 percent chance of completing this activity between 86 and 134 days. B. There is approximately a 68 percent chance of completing this activity between 98 and 122 days. C. There is approximately a 95 percent chance of completing this activity between 98 and 122 days. D. There is approximately a 75 percent chance of completing this activity between 86 and 134 days.

0 Answers  


What is the purpose of the project charter? A. To recognize and acknowledge the project sponsor B. To recognize and acknowledge the existence of the project and commit organizational resources to the project C. To acknowledge the existence of the project team, project manager, and project sponsor D. To describe the selection methods used to choose this project over its competitors

0 Answers  






You are a project manager working for Mail House King. Your company processes orders for several mail-order catalog companies. Your project is to install new mail-sorting equipment and software. You’ve had some problems and experienced some variances so far during the project. You do not expect these variances to continue, as they're atypical. Your project sponsor has asked for an EAC. You know the following information: PV = 800, BAC = 700, EV = 675, AC = 750, and ETC = 30. Which of the following is the correct EAC given the circumstances? A. 25 B. 760 C. 775 D. 833

0 Answers  


Your project's primary constraint is quality. In order to make certain the project team members don't feel too pressed for time and to avoid schedule risk, you decide to use which of the following activity estimating tools? A. Expert judgment B. Quantitatively based durations C. Reserve time D. Analogous estimating

0 Answers  


You are the project manager for Heartthrobs by the Numbers Dating Services. You're working on an updated Internet site that will display pictures as well as short bios of prospective heartbreakers. You've just completed your project staff assignments and published the project team directory. Which process are you in? A. Resource Planning B. Organizational Planning C. Project Development Planning D. Staff Acquisition

0 Answers  


When a project is being performed under contract, the product description is provided by which of the following? A. The buyer B. The project sponsor C. The project manager D. The contractor

0 Answers  


You are the project manager for Lucky Stars nightclubs. They specialize in live country and western band performances. Your newest project is in the Planning process. You are working on the WBS. The finance manager has given you a numbering system to assign to the WBS. Which of the following is true? A. The numbering system is a unique identifier known as the code of accounts, which is used to track the costs of the WBS elements. B. The numbering system is a unique identifier known as the WBS dictionary, which is used to track the descriptions of individual work elements. C. The numbering system is a unique identifier known as the code of accounts, which is used to track time and resource assignments for individual work elements. D. The numbering system is a unique identifier known as the WBS dictionary, which is used to assign quality control codes to the individual work elements. ?

0 Answers  


you are the project manager of a project , customer is asking for a change in scope and agrees that it will be a CR. But you do not want to take the CR for whatever reason. How will you convince the customer in doing so

2 Answers   Samsung, Wipro,


Receivers in the communication model filter their information through all of the following except: A. Culture B. Knowledge of subject C. Conflict D. Language

0 Answers  


Categories