You are the project manager for Heartthrobs by the Numbers Dating Services. You’re working on an updated Internet site that will display pictures as well as short bios of prospective heartbreakers. You have your activity list and resource requirements in hand and are planning on using qualitatively based durations and reserve time to determine activity durations. Which of the following is true?
A. You are using inputs of the Activity Duration Estimating process.
B. You are using tools and techniques of the Cost Estimating process.
C. You are using tools and techniques of the Activity Duration Estimating process.
D. You are using inputs of the Cost Estimating process.
No Answer is Posted For this Question
Be the First to Post Answer
All of the following are types of project closures or endings except: A. Addition B. Integration C. Verification D. Extinction
Which of the following describes the cost of quality associated with scrapping, rework, and downtime? A. Internal failure costs B. External failure costs C. Prevention costs D. Appraisal costs
what do u mean by an interview? no explanations but define.
Your company manufactures small kitchen appliances. They are introducing a new product line of appliances in designer colors with distinctive features for kitchens in small spaces. These new products will be offered indefinitely starting with the spring catalog release. In order to determine the characteristics and features of the new product line, you will have to perform which of the following? A. Fast tracking B. Consulting with the stakeholders C. Planning the project life cycle D. Progressive elaboration
How do you motivate team members?
Which of the following is true? A. Discounted cash flow analysis is the least precise of the cash flow techniques as it does not consider the time value of money. B. NPV is the least precise of the cash flow analysis techniques as it assumes reinvestment at the discount rate. C. Payback period is the least precise of the cash flow analysis techniques as it does not consider the time value of money. D. IRR is the least precise of the cash flow analysis techniques because it assumes reinvestment at the cost of capital.
You are the project manager for a web development project. You hold regular project status meetings and publish status reports on a timely basis. You know that communication is one of your most important functions. As such, all of the following are true except: A. Senders are responsible for sending clear, concise, complete messages. B. Receivers are responsible for understanding the message. C. Communication can be vertical or horizontal or both. D. Effective communication techniques include making eye contact, nodding, and asking clarifying questions.
What are the tools and techniques used in the Initiation process? A. Project selection criteria, historical information, expert judgment B. Project selection methods, historical information, expert judgment C. Project selection criteria, expert judgment D. Project selection methods, expert judgment
What are the triple constraints? A. Time, schedules, and quality B. Time, availability, and quality C. Time, money, and schedules D. Time, money, and quality
what kind of questions can be asked from SDLC for a project leader role?
The Critical Path Method is a mathematical tool and technique of the Schedule Development process. All of the following are true regarding CPM except: A. Determines a single early and late start date and a single early and late finish date B. Calculates expected value C. Focuses on the calculation of float time D. Shows the critical path, or the path with the longest duration
What is the difference between risk impact and risk probability?