Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


how can we decide where we have to DYn11 or other vector
group transformer

Answers were Sorted based on User's Feedback



how can we decide where we have to DYn11 or other vector group transformer..

Answer / ramachandran n

Vector Groups are the IEC method of categorizing the
primary and secondary winding configurations of 3-phase
transformers. Windings can be connected as delta, star
(wye), or interconnected-star (zig-zag). Winding polarity
is also important, since reversing the connections across a
set of windings affects the phase-shift between primary and
secondary. Vector groups identify the winding connections
and polarities of the primary and secondary. From a vector
group one can determine the phase-shift between primary and
secondary.
The first criterion to consider in choosing a vector group
for a distribution transformer for a facility is to know
whether you want a delta-star or star-star. Utilities often
prefer star-star transformers, but these require 4-wire
input feeders and 4-wire output feeders (i.e. incoming and
outgoing neutral conductors). For distribution transformers
within a facility, often delta-star are chosen because
these transformers do not require 4-wire input; a 3-wire
primary feeder circuit suffices to supply a 4-wire
secondary circuit. That's because any zero sequence current
required by the secondary to supply earth faults or
unbalanced loads is supplied by the delta primary winding,
and is not required from the upstream power source. The
method of earthing on the secondary is independent of the
primary for delta-star transformers.
The second criterion to consider is what phase-shift you
want between primary and secondary. For example, Dy11 and
Dy5 transformers are both delta-star. If you don't care
about the phase-shift, then either transformer will do the
job. Phase-shift is important when you are paralleling
sources - you want the phase-shifts of the sources to be
identical. If you are paralleling transformers, then you
want them to have the same the same vector group.
If you are replacing a transformer, use the same vector
group for the new transformer, otherwise the existing VTs
and CTs used for protection and metering will not work
properly.

Is This Answer Correct ?    40 Yes 7 No

how can we decide where we have to DYn11 or other vector group transformer..

Answer / gunasekaran

normally Dyn11 vector group using at distribution
system.because GT are YNd1 for neutralizing the load angle
between 11 and 1. we use Dyn1 at distribution system we r
using GT are YNd11. in some industries 6 pulse electric
drives are using due to this 5thharmonics will generate if
we use Dyn1 it will be suppress the 5th harmonics.

Is This Answer Correct ?    10 Yes 12 No

how can we decide where we have to DYn11 or other vector group transformer..

Answer / praween

Generally Vector group is configure the tranformer primary and seccodry winding with each other....these vector group are diffrent type like as dyn1,dyn11 ,dyn0,dyn6 .we understand the phase difference with niddle of clock..there are30 degree make between two..that means of dyn11 is delta winding laggs 30 degree from star winding of transformer....

Is This Answer Correct ?    0 Yes 4 No

how can we decide where we have to DYn11 or other vector group transformer..

Answer / eng. ahsan rassam

DEPENDING ON TYPE SYSTEM VOLTAGE FOR EXAMPLE IF WE HAVE
33KV AND 11KV WE CHOOSE VECTR GROUP DYN11. AND IF WE WANT
TO OPRET TWO OR MORE TRANSFORMER OR GENERATOR IN PRALLER WE
MUST CHOSSE SAME VECTOR GROP.

Is This Answer Correct ?    6 Yes 18 No

Post New Answer

More Electrical Engineering Interview Questions

if AVR fails in alternator. what will be the effect.

13 Answers   HP,


why in power staions distriution r like 11kv,33kv,66kv in india?

4 Answers  


What are different types of control systems?

0 Answers  


what do you mean by leading power factor & lagging power factor

13 Answers   Suzlon,


can three phase induction motor rotate with only 2 phases connected

22 Answers   Delta, Mannar Company, Suntron,


definition of transponder?

1 Answers  


What is maximum rating of transformer ?

2 Answers  


HOW DO WE COLLECT THE SOLAR ENERGY AND DESCRIBE THE METHODS TO CONVERT THE SOLAR ENERGY INTO ELECTRICAL ENERGY?

1 Answers  


how to calculate the current carrying capacity of a conductor. How it is related to diameter of cable or conductor

3 Answers   AGC, BARC,


Stator core loss of squirrel cage induction motor compared to rotor core loss is= A equal B more C less D depends on load

2 Answers  


Diagram on interconnectivity of 11kv transformer with RMU (i.e, one incoming and two outgoing or two incoming and one outgoing)

0 Answers  


IN bateery size of positive is biger than negative .why?

8 Answers   Power Grid,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)