how we can calculate the capacity of a proposed canal in a
command area.
Answers were Sorted based on User's Feedback
Answer / khalil
first of all duty of the command area is determined. Then
we multifly discharege into acres. for example if duty 1
cusec/100 acres the area is 1000 acres then discharge of
the canal is 10 cusecs. if the canal shape is trapezoidal
then we put by hit and trail method varous d and b.
Is This Answer Correct ? | 8 Yes | 2 No |
Answer / ruchi
FIRST OF ALL IT IS very clear here tht it is ALRDY BEEN
PROPOSED so the Govt or d org. engaged in it has alredy
calclted it but still if we wnt 2 calclte thn, simply we
have 2 aply h'r' d basic mathematical formulaes 4
calculating capacity by alalysing it's given measured data.
Is This Answer Correct ? | 1 Yes | 3 No |
4. What is your philosophy / attitude towards work?
whta are the types of columns
what is pH value of sewage&water.if pH value is given then how to calculate H+.
how can economic during construction of a project.
calculate 1-2-4 ration concrete - cement - sand metal and water required for 1 cum
What is the unit weight of steel?
I am in India. Employer A got approval for my H1. But they have no job for me now. Company B is going to file H1 for me. They do not know about company A. Is there any way that I get approved H1 of company A transferred to Company B?
What do you mean by Hydraulic Piling??
what is the difference b/w GSB and WMM?
How much steel required for 1 sq. meter area?
1 Answers Aditya Constructions,
what is daily progress of a steel fixer average how many kilograms he can fix in 8 hours average
1 Answers Al Latifia Trading Contracting,
Why did you choose this career?