Answer / ns satyaraj

Purging is flushing out unburnt fuel in flue gas path. scavenging is removal of flue gases which are still in flue gas path. It is done before lighting up the boiler for certain defined period say 300 sec with fd fan air. Also purging of burners are done to prevent choking of burners passages of fuel. Done after burners are cut out of service . There is a risk of explosion if not done mostly in oil fired boilers

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More Power Plant Engineering Interview Questions

LAPT working in alternator / generator

0 Answers   Power Plant,


By any way can we increase the B check hours from 300 to 500

0 Answers  


what is the formula for converting mmwc to tph in a dp type transmitter.what is the range in plc(in tph) if dp tx.range from 0 to 5000mmwc.

2 Answers   CCC, Korba Power Plant, Shyam Steel, Utkal Alumina International,


Why we need to maintain furnace and secondary air dp.if it increase or decrease what happens.

1 Answers  


If a pump has "N" no .of conections in the discharge. If a connection has a heavy leakage. Then it's motor current get affected or not??

1 Answers  






what's interlock relay ?

3 Answers   International Mega Food Park Limited, National Power Training Institute NPTI,


By seeing a Power house Can we justify the kV of that power house?

1 Answers  


A 5A rewirable fuse blows when 9A flows.determine the fusing factor?

1 Answers   Schneider, Student, Tata Power,


What is droop.

2 Answers   Dhampur Sugar Mills, Elaf,


Qatar Fertiliser Company (QAFCO) Shortlisted me for interview (got the intel from my source) for Field Operator- Utilities post. Please let me know what kind of questions they asked? ... this position requires 5 years of experience in Power Plant and background Diploma in Electrical/ Mech. ... my Background is Electrical and I am a sub Assistant Engineer (Operation) at a private HFO based Power plant... PS: Please Let me know what preparation should I take to obtain the Interview which will be take place In Bangladesh soon

0 Answers  


what's the moog valve

0 Answers   Sirte Oil Company,


Why cold water is used for Boiler Hydro test

1 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)