How gate result to cube for 7 day?
Formula for the cube testing?
Answer / ajmal khan
Days
--------------- X Fck
4.7+ 0.833 days
For Example M20 =
7
--------------- X 20
4.7+ 0.833*7
= 13.29N/sqmm. Aproximately 1/3rd of 20N.
We can find for any day of any grade.
| Is This Answer Correct ? | 6 Yes | 1 No |
While Calculating Quantity Of cement,sand,Metal we get cement in no of bags,Where Sand & Metal we get in Meter Cube(M3)how to convert it to Units(i.e in no of lorry's or Tractors )
what do u mean by elongation & flakiness of aggregate?
why we always consider Bulkage due to the voids only for the Fine aggregates not for the Coarse aggregates
how calculate the ms beam weight?Please give me formula details?
pls tell me about method of cutting length of ties column
On concrete surface 1sq.ft area hacking no's of hack?
Specific gravity of cement?
Why we select pile foundations
Isolated square footing quantity calculations
plz tell me one brick total plaster area?
9 Answers Aparna Constructions, Aparna Enterprises, L&T,
why primer application is required before applying putty
What is the lap lenth for welded joints for reinforcement bars. and what is its IS code no.
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)