How to calculate the amount of Brick,cement & sand required
for 1 cum of 115mm thick brick work with ratio 1:5 please
give me an answer with detailed step
Answer / santosh
.240*.085*.10 = 0.00204 m3 with morter qty per brick
without morter qty of brick = .23*.075*.1 = 0.001725 m3
then 1/0.00204 = 490 bricks
= 490 * 0.001725 = 0.8456 only brick in m3
wet morter qty = 1- 0.8456 = 0.1544 m3
dry morter qty = 0.1544 * 1.32 = 0.204 m3
0.204/6*1cement = 0.03397m3 cement
cement = 0.03397 * cement density 1470/50kg per bags = 1 bags
sand 0.03397 * 6 =.204 m3 sand
sand in brass = 2.83 m3 = 1 brass 0.07208 brass
| Is This Answer Correct ? | 2 Yes | 1 No |
why crakes are developped in opening corners
what is mean by bulking of sand?
One unit equal to how many brick
3 Answers Sainath Infrastructure,
how many covering can be taken in the beam,column & slab also stair-case?
reinforcement slab, beam and column formulas?
What is the purpose of the gap in the road on this bridge?
how to calculate steel quantity of column from steel design
PLS.......... ANY ONE CAN FORWARD ME PREVIOUS QUESTION PAPER hpcl civil engg
Why ss Steel is not using in RCC concrete.
what is bending moment, for simply supported slab ? how do you calculate ?
WHAT WII BE THE WATER ABSORPTION POWER OF WOOD ?
In Fe415 & Fe500,What is mean by "Fe" and "415/500"?
12 Answers CMR, Modi Builders, Taehwa Enterprises, vvip,
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)