Before erect the instrument what should you do?

Answers were Sorted based on User's Feedback



Before erect the instrument what should you do?..

Answer / jspatel

One should confirm whether it is isolated and drained

Is This Answer Correct ?    2 Yes 1 No

Before erect the instrument what should you do?..

Answer / ahmedallam

verify the instrument with technical data sheet and spec

Is This Answer Correct ?    2 Yes 1 No

Before erect the instrument what should you do?..

Answer / fazil

one should have work permit..operator will control the signal manually.. close primary valve and manifold also
drain existing liquid or gas by drain plug.

remove termination and glanding also tape it to avoid short.then you can remove instruments

Is This Answer Correct ?    1 Yes 1 No

Post New Answer

More Instrumentation Interview Questions

what is datum line?

4 Answers  


please explain about actuator action? direct action & return action ?

1 Answers  


Draw a simple circuit for a well head control panel used to protect the well against fire, leak, blockage, ESD, & controls the operation of one downhole & one surface safety valve. Explain the operation and controls

0 Answers  


what is see back effect?

9 Answers  


what is compensation? temprature & pressure

0 Answers  






Is there’s power on the bus (if so, state whether on the signal bus, or on a separate in the following: a) HART b) Profibus DP c) Profibus PA d) DeviceNet e) Foundation Fieldbus

1 Answers   EIT,


what is the advantage by using PID controller than P& PID?

1 Answers  


how many types of preheaters are in cement industry & what r they can any body explain?

0 Answers  


what is field bus system. need defination

3 Answers   Takreer,


why we used for range in pnumatic 3-15 psi and current 4-20 ma?

11 Answers   Jindal,


How many ohms are required for proper earthing?

0 Answers  


Dear all... I have 1 0-400 duplex type RTD, I connected the A side to the temperature indicator and B side to the PLC panel, but when I have observed then found that The PLC side temp has the variation. and it was distub to other RTD temp also. so what can I do.

1 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4452)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)