if we make b.b.s then bend correction is taken how much..
Answer / sachin
cutting length= total length-2*Dia of bar*no.of bends
| Is This Answer Correct ? | 4 Yes | 0 No |
what is difference between bending and twisting
silt maximum in sand.
List out some of the common problems that architect have to tackle it?
what qualifications did you need to become a civil engineer?
Define slump in terms of slump test
In beam where lapping is allowed for top and bottom bars?
1 Answers IOCL, JMC, JMC Projects,
what is PEB structure
Types of pile, which should be prefer in sandy soil
Why provides hook of stirrups only ones side?
How many steel is require in one cubic meter area?
Please give me the mixing ratio for higher grades of concrete (M30, M35, M40, M45, M50) using cement, VSI sand (Maharashtra) and metal. In case any other additives are supposed to be added to my concrete please let me know about that as well.
How to find the volume of wood(tree) from its height and circumference.(circumference-6'5" and height 3'2")??
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)