How many bricks are required for 100 sq ft 5" & 3" wall, Brick size= 230x115x75
Answers were Sorted based on User's Feedback
Answer / md shamim
5 inch thickness wall 100 sqft req. 480pcs bricks
and 3 inch thickness wall req. 100 sq ft. is 280 pcs bricks
Is This Answer Correct ? | 7 Yes | 2 No |
Answer / atul jadhav
For 100 sq ft = 100÷ 10.764 = 9.29 sq my
For 5" = .125 m
For 3" = .075 m ( also note generally brick work is more than 4" )
Therefore for 5" volume will be
V= 9.29 (area) x .125 (thickness of wall)
V= 1.1613 m3
Now volume of brick having size - 230x115x75 is = 0.001984 m3
Therefore no of bricks = 1.1613/0.001984 =~ 585 nos ( without considering mortar)
Same for 3" bricks no of bricks required= 0.69675/0.001984 =~ 351 nos
(If mortar considered then size of brick will increase by 10mm from all sides)
Is This Answer Correct ? | 0 Yes | 0 No |
plz.show development and anchorage length in simple diagram.
can we find any technical issue if we are gong to change the dimensions of steel beams from one type to another type IE if there are any equievelant data base to find solution for problem of changeing sectios of beam from one type to another with the same cross sectional area.
100mm block work 64 bags of cement used 150mm block work 286 bags of cement used 200mm block work 20 bags of cement used patly work (M15) 293 bags of cement used mortar ratio is 1:5 how to calculate volume of sand in cum & no. of bags
what is the venturi effect in buildings? what is green house concept?different types of dams? which dam is economical arch dam or gravity dam. what are the conditions favourible to both of them?
Why we are using 150 mm X 150 mm X 150 mm cubes for testing the compressive strength of concrete in CTM and why not other sizes?
what is injection grouting and what is rewiring.
what is plum concreting and how is it can be done what is the ratioo of rubble and concrete
What is Well Point System in Dewatering
what is the diferance np3 and np4 pipe
1 Answers Sharda Construction,
Kindly furnish the relation between 7 days strength & 28 days compressive strength of Cement Concrete cubes. Can you clarify whether the relation gets altered due to WATER- CEMENT ratio?
How to calculate the quantity of water in cement mortar eg. CM 1:3?
Should column area deducted from form work measurement of slab in building?