How to Determine the Quantity of Cement Sand , Aggregete
and Reinforcement Bars in 30 feet X 40 Feet and Height is 4
Feet .
Answer / prabu
1 feet = 0.3048 meter
30'*40'*4' = 9.144 *12.192 * 1.2192 meter
total volume = 135.92 meter cubic
1 bag cement = 50 kgs
unit wt of cement = 1440 kg/m3
density = weight/volume = 50/1440 = 0.0347m3
if concrete grade is M20 and ratio is 1:1:2
1+1+2 = 4
cement = 135.92/4 = 33.98
33.98/0.0347 = 979.25 bags
1 cement bag = 50 kgs, so
979.25 bag = 979.25 * 50 = 48962.53 kgs
sand = 1* 33.98 = 33.98 m3
aggregate = 2*33.98 = 67.96 m3
for slab = 0.7 -1% of concrete volume (reinforcement provided )
for beam = 1 - 3%
for column = 1 - 5 %
for footing = 0.8 - 8%
in this problem = 135.92 m3 concrete
for slab = 135.92 * 0.007 = 0.95m3 volume reinforcement provided.
ans =
cement = 48962.53 kgs or 979.25 bags
sand = 33.98 m3
aggregate = 67.96 m3
for slab = 0.95m3 volume reinforcement provide
Is This Answer Correct ? | 9 Yes | 5 No |
what is ment by surveying?
What should be the size (Cubic meter) of a water tank for 1000 Ltrs. capacity?
What is the calculation for finding cement and sand for 10' * 12' area ratio 1:6 thickness 12 mm
What is braced excavation all about?
The point of contraflexure occurs in
If u want ur Ans.Of any Question so mail me skatiyar011@yahoo.in
what should be RCC material i.e iron rod(mm)x cement x stone x sand for laying of slab L 42'x B 22'x tk 0.375ft = 1nos & column of H 17'x15"x8" 2nos.
If a slab concrete is placed with M-20 grade concrete, actually it has to be placed with M-30. what are the rectifications / measures to be taken after concreting is done.
What is the difference between the concrete mix design carried out by IS10262 and by ACI method ?
sir tell me what are the rules to find out the cut length? and what is the deduction in dia to be made ?
What is the proportion of M30 to M80and which construction these are used
how we can calculate the capacity of a proposed canal in a command area.
5 Answers KPL, MPPSC Madhya Pradesh Public Service Commission,