what is the slump of pile concreting work? give me the value
of minimum and maximum value of slump and how give slump in
pile?

Answers were Sorted based on User's Feedback



what is the slump of pile concreting work? give me the value of minimum and maximum value of slump ..

Answer / gouda_civil33

minimum 100mm maximum 200 mm

Is This Answer Correct ?    6 Yes 0 No

what is the slump of pile concreting work? give me the value of minimum and maximum value of slump ..

Answer / senthil kumar

140mmto180mm slump
alloved for pile
concreate

Is This Answer Correct ?    6 Yes 0 No

what is the slump of pile concreting work? give me the value of minimum and maximum value of slump ..

Answer / englitu

The slump for pile, we use generally, is around 6 inches. The last part of your question, that is "how give slump in pile", is not clear to me.

Is This Answer Correct ?    2 Yes 1 No

Post New Answer

More Civil Engineering Interview Questions

how to check the quality of sand?

5 Answers   L&T,


UNIT Weight of 40mm, 20mm, 10mm Stone Aggregates

2 Answers   Afcons,


What Is the Thumb rule to calculate depth and dia of pile required to carry specified load on differeent soil

0 Answers  


Why should you consider yourself fit to be hired by jindal steel.

0 Answers   Capital IQ,


how to calculate the steel quantity for columns and beams

7 Answers   CMR,






you are planning to paint a newly fabricated workshop building made of structural steel of 10 tons total mass.you are require to paint 1 cot of primer and 2 coats of top coat.How many liters of primer and top coat you will request

2 Answers  


how 2 find out slap steel quantity ? plz help me

1 Answers   NCC,


Why we use Reinforcement out side of the column not in centre

4 Answers  


WHAT IS YOUR CURRENT SALARY

0 Answers   VGN Developers,


how much brick,cement,and sand required in 1cum brickwork(1:4)

8 Answers   JMC, RK,


What is the difference between normal brick & concrete hollow blocks in all aspects?

4 Answers   BTP, DMU, L&T, PSC,


Kindly post me previous year interview questions with answer for post of DY. Manager (civil engg.) for GAIL, NTPC, IOC, OIL and ONGC etc.

0 Answers   GAIL, KOC, Megha Constructions,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)