Middle point of any slab is raised 10-12 mm during shuttering work because–– ..

Answer / mughalsab

if i dont raised at mid ponit of slab so when we poured concrete then the slab is sag at mid point due to its own weight therefore we raised at mid point so when concrete is poured then the slab is going to its corect position.

Is This Answer Correct ?    9 Yes 1 No

Middle point of any slab is raised 10-12 mm during shuttering work because–– ..

Answer / rj

so as to have a camber at the middle area.

Is This Answer Correct ?    8 Yes 4 No

Middle point of any slab is raised 10-12 mm during shuttering work because–– ..

Answer / bharat gurav

because at middle point act point load & share force act at
L/4 so extra steel r provided...............but at mid-span
no provide extra steel due 2 sla raise 10-12mm

Is This Answer Correct ?    1 Yes 4 No

Middle point of any slab is raised 10-12 mm during shuttering work because–– ..

Answer / amar kantak

FOR POURING CONCRETE

Is This Answer Correct ?    0 Yes 8 No

Post New Answer

More Civil Engineering Interview Questions

which is cover of r.c.c. column,beam and slab

5 Answers   Cube, RPP,


tell me quantitys of matal, sand and cement in 1:4:8 and 1:2:4

9 Answers   AVL, Infosys, NCC, SPCL, Swapnapurti Developers,


25. Are you willing to work overtime?

6 Answers  


what is mean by Face bar using in coloums?

1 Answers  


how much used soil in 1 brick of standard size?

0 Answers   Global Career Solutions,






What is the sugested procedure of water purification for public supply?

0 Answers  


shuttering consumption per square feet in multi storeyed building?

6 Answers   L&T,


How can we calculate quantity of slab, beam @ column ? Beam should be calculated by deducting slab thickness or slab should be calculate in to in ?

5 Answers   SMC,


Whats the difference between uniaxial column

8 Answers  


What is Shoe Footing ?

2 Answers   Bhandari Associates,


why there is need to provide shear reinforcement?give the basic reason?

9 Answers   JMC, L&T, Power Grid,


which type of materials should be used for framed structure???

9 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)