How much steel and concrit required in 1000 square feet
slab?
Answers were Sorted based on User's Feedback
Answer / shivaji yadav
Steel = .12*1000/10.76 *90 = 1003.72Kg = 1.0 MT
Concrete = .12*1000/10.76 = 11.15 Cum
Is This Answer Correct ? | 19 Yes | 10 No |
Answer / swaminathan
Assume Slab Thickness 120 & Steel 80kg/Cum
Steel = .12*1000*80 = 9600 kg = 9.6 MT
Concrete = .12*1000 = 120 Cum
Is This Answer Correct ? | 12 Yes | 23 No |
Name the standard sand for concrete tests
what is the load capacity of bored pile pile dia 500mm
Define road.
what is the difference between NP2 Class and NP3 Class RCC Hume pipes
Where are laterally loaded piles are used in practice?
07. 4 main points about check list for rebar works are– ––
Weather we heat cement, will it changes its color? if yes why? if no why?
What is the difference between M20 and M25 concrete?
relation bet Coefficient consolidation Cv, time factor Tv, drainage path d, & time t is Cv=d2Tv/t Cv=d2t/Tv Cv=tTv/d2 Cv=Tv/td2
what is the formula to calculate costing of rubble soling and wbm in road works?
how to calculate concrete quantity for footing using M25 grade 1:1:2 for 730cft.
What is the diff. Between rectangle & parallelogram?