Steel calculation formala for column,beam and slab.
Answer / vijay kumar.g
beams:(is 456-2000)
mini Asv =(0.85*b*d)/fy
maxi not greater than0.004bD
columns:(is 456-2000)
mini 0.8% of gross c/s area of the column
maxi not more than 6% of gross c/s area of the column but pratical purpose used 4% of gross c/s area of the column
slabs:(is:456-2000)
mini 0.15% of c/s area of the slab this value can be reduced to 0.12% when used HYSD bars
Is This Answer Correct ? | 11 Yes | 1 No |
Respected sir i am appearing for the exam this year.I will be highly obliged if u kindly send me last year's interview paper on civil engineering in my email address debosmitroy@yahoo.in
How many bags required for 1cum grouting?
Minimum and maximum size of the building components
How much steel required in one cubic meter RCC Main girder
What is the finess modulus of sand?
You have 3 snd sample of different FM=0.21,FM=0.95,FM=2.90 which one is suitable for a)plastering on R.C.C b)plastering on masonary wall c)concreting column d)concreting of bored pile.also justify your answer.
Explain different types of rcc pipes.
why do you desire to change from your current position?
how many cubic feet in one unit of sand?
16 Answers L&T, PSPCL, Ratna Infrastructure Projects,
Can a 24" RCC beam can rest on 18" RCC beam.
The definition of national highway
what is tension footing?
0 Answers Wah Engineering College,