Steel calculation formala for column,beam and slab.
Answer / vijay kumar.g
beams:(is 456-2000)
mini Asv =(0.85*b*d)/fy
maxi not greater than0.004bD
columns:(is 456-2000)
mini 0.8% of gross c/s area of the column
maxi not more than 6% of gross c/s area of the column but pratical purpose used 4% of gross c/s area of the column
slabs:(is:456-2000)
mini 0.15% of c/s area of the slab this value can be reduced to 0.12% when used HYSD bars
| Is This Answer Correct ? | 11 Yes | 1 No |
What is the quantity of steel, cement, sand, and aggregate required for a 2100 sq ft Roof Slab(Residential Building) area of RCC?
can you provide a link for manual design of building?
what is the diffrence of opc and ppc cement ? expailn
calculate the cost for AAC block wall of 15cum?
how much quantity are required like cement,sand,aggregate for (46*29*0.41)feet slab? how much this quantity can be calculated?
can any1 mail me IS CODES and quality check sheet of materials..? its urgent plz
what is the quantity of cement( in bags),sand and aggregates required for 1 cmt of M 25 concrete
how can we calculate steel value, depending on load
How much actual % of wastage of steel.
Soil Mechanic: You are building a gravel road. How much water do you need to mix in compact 100 m3 of road quantity borrow pit gravel?
WHAT IS THE IMPORTANCE OF FLY ASH BRICK?
How much standard bricks required for a wall of 9*1200*1200 inches
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)