what is the minimum spacing required for slab & beam
reinforcement
Answers were Sorted based on User's Feedback
Answer / subhasbabu
FOR SLAB FOR MAIN BAR 3 TIMES THE DIAMETER AND 5 TIMES FOR
DISTRUBUTION BAR, BUT IN THE CASE OF BEAM MAXIMUM SIZE OF
AGGREGATE, AND MINIMUM BARS 2NOS FOR MAIN REINFORCEMENT
| Is This Answer Correct ? | 7 Yes | 2 No |
Answer / piyush singh
slab : maximum spacing should not exceed
main steel = 3 * dia or 300
distribution = 5 * dia or 450
as per IS 456
| Is This Answer Correct ? | 4 Yes | 0 No |
Answer / puspendu shyamal
minimum spacing required- (a)Diameter of the bar if the diameter is equal,(b)Diameter of the largest bar if diameter is unequal,(c)5mm more than the size of the aggregate,which ever is greater.
| Is This Answer Correct ? | 3 Yes | 1 No |
how to nfind out the specific gravity of sand.aggregate,water please help...
how much steel provide in 1m cube r.c.c
develpement lengh
what is the ideal construction joint for slab?
I used Etabs software to analyse a high-rise building. And I want to use templated UBC-codes inside to calculate the Seismic load. My question is: whether or not I have to control the seismic load by base shear load which is manual calculation? (just for more clarification: I can control this by input the scale factor into Eartquake definition in Etabs) I would highly appreciate your answer.
infosys campus ques... u drive a car,nmb of d car is KA17M8719. it leaves at10:26am frm davanager to bangalor which is264km away at a speed of 95km/hrCar reachs bangalor at 4:18pm. nw tel me wat is d date of birth of drvr
9 Answers Ernst Young, Infosys,
Define a polyline?
why 50% more is assumed while calculating dry volume of coarse and fine aggregates in concrete calculations.whether 50% more is correct? How is it decided? whether the same is applicable to cement volume. Also what about cement mortar dr volume? How much more is to be considered for dry volume of mortar.
how much sand requires for Light weight blocks for 100sqft
Manpower required for de shuttering of conccrete slab
WHAT HAPPEN WHEN USING OF LARGEST POSSIBLE MAXIMUM SIZE AGGREGATE RATHER THAN SMALLER AGGREGATE IN RCC ?
How much for the BRC lapping in full yield and half yield < and which table to get it ?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)