how many brick sand cement require (1:5) 1 cum
Answers were Sorted based on User's Feedback
Answer / m.a. haleem akmal
473 Bricks, 0.232 cum Fine sand and 1.31 bags cement
| Is This Answer Correct ? | 10 Yes | 1 No |
Answer / jayanth
1/(.2*.1*.1)=500 Bricks
qty of cement=1*1.5*1444(density of cement)/6=361kg
sand=1805
| Is This Answer Correct ? | 4 Yes | 2 No |
Answer / ajayzarbade
total no of bricks=500 nos with inc. wastage
& 1cu.m bk.work 33% dry morter then ratio will be use 1:5 so
1/6=0.166m3/0.035
| Is This Answer Correct ? | 0 Yes | 0 No |
How to do lineout of building
Please can anybody let me know how to calculate cement, sand & aggregete content for one meter cube of concrete. please if possible provide calculations for cement in no. of bags, sand & aggregate in cu.mt. Thanks.
What is meant by Anchorage length? Development Length?
pls tell me about method of cutting length of ties column
In Residential home construct footing,beam, column,lintel,rcc roofs which dia rod used how to self assumed
What is the life of reinforcement?
what pressure the NP2 class RCC pipe can sustain?
how to doing or how to prepare the or which things can be done on the site when construct the building?
types of piles detail,
0 Answers DLF, IVRCL, JP Group,
how much cement and sand required for 1cum rr masonry
what is difference between fe 415 and fe 500
11 Answers CCCL, ECC, Hariharan Foundations,
how to calculate required shuttering material like props,spans,plates ..etc for a slab?
1 Answers NCC, Shoba Devlopers,
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)