how much aggregate need for 1:4:8 p.c.c in 1sqm area?

Answers were Sorted based on User's Feedback



how much aggregate need for 1:4:8 p.c.c in 1sqm area? ..

Answer / ashutosh

I think the question is wrong bcoz we calculate the concrete
in volume(cubm) not calculate from area(sqm).
If it is volume(cubm)then we need the depth of PCC

Is This Answer Correct ?    8 Yes 3 No

how much aggregate need for 1:4:8 p.c.c in 1sqm area? ..

Answer / madhusudhan reddy

what is the thickness of concrete?

Is This Answer Correct ?    0 Yes 0 No

how much aggregate need for 1:4:8 p.c.c in 1sqm area? ..

Answer / pradeep

we calculate the concretein volume(cubm) not calculate from area(sqm).
in 1:4:8 PCC we use thickness 0.075Meter.
we know that in this ratio cement consumption will be 3.3 bags per cubic meter,
in one bags weight 50kg.
according to above we can calculate

Is This Answer Correct ?    0 Yes 1 No

how much aggregate need for 1:4:8 p.c.c in 1sqm area? ..

Answer / shree.manthalkar

.68 m3

Is This Answer Correct ?    5 Yes 7 No

how much aggregate need for 1:4:8 p.c.c in 1sqm area? ..

Answer / sahil

i think it needs 8 buckets of aggregates in 1 sqm area.
according to ratio given..

Is This Answer Correct ?    0 Yes 7 No

Post New Answer

More Civil Engineering Interview Questions

what is the diffrence betwen one way salb & two way salb?

7 Answers   Harmer Simmons,


what is the code provision for acceptance of fineness modulus range for fine aggregates in design mix

1 Answers  


What is the basic difference between QA and QC

1 Answers   CTG Global,


How do you measure water flowing through 300mm diameter pipes?

0 Answers  


formula of calculation of weight of steel bars

15 Answers  






how many bags of cement are needed to make a cement mortar of 1:3

5 Answers   ABC, DBL, DHFL Dewan Housing Finance Corporation, VV, WADAN,


what is a pitot tube

5 Answers  


1. How do you handle non-productive team members?

4 Answers  


Meaning of m20 and m200 concrete

10 Answers   WBPSC West Bengal Public Service Commission,


why we designed limit state method?

1 Answers  


How to calculate labor requirement or requirement of labor projction for a proposed multistoried building for which quantities of different items of work has been already calculated stage wise ?

3 Answers  


What Is the Thumb rule to calculate depth and dia of pile required to carry specified load on differeent soil

0 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)