cement constant for brick works
Answers were Sorted based on User's Feedback
Answer / senthilkumar
if we consider 1:6 ration for cement morter , the cemnt
weight will be 240 kg per m cube morter, normaly 10% volume
of morter will be consume for brickwork of volume. if 25%
means 0.250 m cube morter need for 1 m cube brick work, so
cement need for
calculation;
1:6
1/6*1440kg=240kg
if morter require=.25 m cube
=.25*240=60 kg cement required
| Is This Answer Correct ? | 9 Yes | 6 No |
Answer / gopal
cement constants can be calculated if we know the ratio
cement and sand.
| Is This Answer Correct ? | 1 Yes | 1 No |
How to calculate soil bearing capacity of soil?
plz tell me max persantage of sand for every mix design by volume or weight.
What is unit weight of 1st class bricks ?
What is Rankine Cycle?
What is BDF flooring?
minimum thickness of pcc 1;4;8 for road concrete
Why stag rod provided in roof truss.
which is code is used for design of steel structure
What is the compressive strength of noramal clay bricks and AAC bricks??. which one is better for load bearing wall//
2 Answers College School Exams Tests,
Deduction in length of reinforcement steel for bar bending
How to check the quality of cement?
How much Pressure will apply in Water proofing Grouting method to fill the crack in beams or slabs?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)