Answer / natha
inductive lagging
capacitive leading
resistive unity(perfect unity not practically possible)
zero worst case scenario
lots of trouble
Is This Answer Correct ? | 4 Yes | 0 No |
Your question is know about the power factor of an inductive
load, thus only one answer is LAGGING.The other factors are
also given to you to understand
1.inductive ---lagging
2.capacitive ---leading
3.resistive ---unity(perfect unity not practically possible)
4.zero--- worst case scenario lots of trouble
Is This Answer Correct ? | 1 Yes | 0 No |
What kind of preventive maintenance are there for AC induction motor?
What are the different types of circuit breakers?
will we have to design the UPS differently for both i.e. if we want to connect the two batteries in parallel and/or we want to connect the two batteries in series ?
in breather of transformer how sillicon gel absorb the moisture?wat happen when the moisture in that oil?
Sir,In our company there are 3 caterpillar make(capacity:(1) 3.3KV,2.5MW(2)3.3KV,2.5MW & (3)3.3KV,1.9MW) & 1 deutz make (capacity:11KV,3.8MW)gas engines utilised,all are running in paralell. There are three transformer utilised,(1) 6.25MVA,3.3KV/22KV,Impedence voltage:6.7% used for two generator,both are 2.5MW(2)5.5MVA,3.3KV/22KV,Impedence voltage:7.2% used for one generator of 2.5MW & (3) 5.5MVA,11KV/22KV,Impedence voltage:7.8% used for one generator of 2.5MW.all generator breakers capacity of 1250Amps. Sir,I want the details of fault level calculation of generator,transformer individually & for whole system. If you require any information from me.feel free for contact me sir.pl.send the answer of my question as the earliest as possible.
how power saving takes place through VFD?
advantages & disadvantages of Lagging and leading power factor .
I am in last year of Engineering.I want to apply for ONGC on GATE based score.They require Certificate of Competency as Electrical Supervisor.How can i get this certificate so I can apply for AEE(ELECTRICAL) in 2016
can the measured percentage error during calibration of single phase energy meter be negative?
i have a Connected Load of 280KW and Maximum Demand of 224KW to one of SMDB under design with me. which criteria should i consider to design panel and main cables connected Load or Maximum Demand 1)Breaker rating 2)Panel Busbar rating 2)Incommer cable sizing (ignore Voltage drop)
1.WHAT ARE TRANSMISSION LINE LOSSES DURING WINTER AND SUMMER SEASON? 2.WHAT ARE THE CAUSES/ 3.WHEN THE CORONA IS MORE?.,WHETHER WINTER OR SUMMER? 4. WHAT IS THE PERCENTAGE OF LOSSES IN TRANSMISSION LINE?
tell me about sf6 breakers