How do you calculate qty for form work like props shuttering
sheet and acro span for residential block ?
for Example: 10 sq mt what is the material and qty require to
do form work.
Answers were Sorted based on User's Feedback
Answer / narayani upadhyay
I am not sure too much about it, but it gives an idea for calculating the props , number of sheets and acrospane in a building form work.
size of ms sheet (steel sheet)= 2' * 3'=6 6sqft
props should be between 500 mm to 600 mm to each-other.
Acrospane are uses from one end to other end for supporting the ms sheet on slab.
lets assume the size of 2 BHK = 1000 sqft
=Number of sheet required =1000/6=166.67 approx=170
Add 10 to 15 % wastage=170*1.10=187
=If depth of slab less than 175 mm = 4 sheet contain 1 acrospane.
= If depth of slab more than 175 mm=5 sheet contain 1 acrospan
= lets assume depth of slab= 125 mm
= Number of acrospane= 187/4=46.75 approx=50
=number of props requred= it depend on the size of beam and length of beam around the slab.Total length of beam in running meter around the slab(incuding sunken,balcony ,ots and staircase)=70 m
=props should be between 0.5 m to 0.6 m.
=number of Props for BEAM length=70/0.6=116=approx 120
=Number of props for slab=50*2=100
= Total number of PROPS=320
| Is This Answer Correct ? | 26 Yes | 7 No |
Answer / thamaraikani
simple constructin material calculation:
sheet,span and props
assuming :1000sqm builtup area
step1:sheet
1000/0.9*0.6=1851nos
step2:span
note:(slab thickness less than 175=4sheet)
(slab thickness more than175=5sheet)
span=1851/5=370nos
step3:props
note:(slab thickness less than 175=4sheet/2)slab thickness less than 175=5sheet/2)
props=370*2.5=925nos
| Is This Answer Correct ? | 6 Yes | 3 No |
What is the quantity of cement used for stone pitching work of 100sqm 225mm thick and cement mortar of 1:6? And how?
what is the weight of 12mm aggregates?
Design a reinforced concrete combined footing (rectangular) for two columns located 3.60 metres apart. The overall sizes of the columns are 40cm x 40cm and 69cm x 60cm and the loads on them are 1000 kn and 1500 kn respectively. The space available for the width of the footing is restricted to 180cm. The S.B.C. of the soil is 280 kn/mm2 use M15 concrete.
Can fly ash bricks can be used in brick bat coba?
What is geopolymer based concrete?
what is the code for classification of bricks
For the construction project what capital cost has to be taken in consideration?
how much bentonite powder mix in 1000ltr fresh water with detail.
how do measure the safe bearing capacity of soil? what is the compresive strength for concret?(max.&min.)
What is meant by End contractions
if 20mm & 10mm coarse aggregate we have consider same prapotion than how to analysis m25 concrete
How and where from do we get 162 for calculating sectional weight of TMT
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)