what will be the quantity of matterial and water for pcc in 1
cubic meter , the ratio is 1:4:8 (cement:sand:aggr) ?

Answers were Sorted based on User's Feedback



what will be the quantity of matterial and water for pcc in 1 cubic meter , the ratio is 1:4:8 (ce..

Answer / australian

for cement,

Dry volume=1.57 cum

so 1.57/13=0.12*1440=173.90 kg

Number of bags=174/50=3.5 bags

and water=85 liters

Is This Answer Correct ?    8 Yes 3 No

what will be the quantity of matterial and water for pcc in 1 cubic meter , the ratio is 1:4:8 (ce..

Answer / manikandan

cement-3.3bags
fa= .465
ca= .96
water= 47.5 li

Is This Answer Correct ?    3 Yes 1 No

what will be the quantity of matterial and water for pcc in 1 cubic meter , the ratio is 1:4:8 (ce..

Answer / uar

For any grade of PCC

1 Cum. wet concrete needs = 1.52 Cum. dry ingredients.

Cement = 168.34Kg / 3.367 Bags
Fine Aggregate = 0.467 Cum. / 16.52 Cft.
Coarse Aggregate = .935 Cum. / 33.34 Cft.

Is This Answer Correct ?    1 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

why the horizontal crack occoured in the joint between brick work and lintel?pls. give clarification???

4 Answers  


Please let me know about answer for my Question as "What is the maximum wastage allowable of HYSD Steel in any Bridge project as per Code and Code reference also ?

0 Answers   Amit Enterprises, ICT,


How to deduct block quantity from the slab quantity for concreting for slab.????

1 Answers  


Hi all, need Staad Pro V8i tutorial

1 Answers   Modi Builders,


What is "Bending moment"? Demonstrate on theory not for formula.

3 Answers  






How bonding is done for composite massonary?

2 Answers   Tarmat Infrastructure,


What is the ratio of cement,sand,aggregate of mix m25

9 Answers  


weight of 1 cft 10mm, 20mm, 40mm aggregate weight of 1cft course sand

0 Answers   Tanishq, Target, Yahoo,


Prepare a Schedule for a Highrised building from starting stage to Handover?

0 Answers   bscpl,


how you calculate the data (all parameter) after transient response method i.e.pile intigrity test on pile.

1 Answers  


which tests for concrete pouring period at the site?

5 Answers   Al Turki, L&T,


rate analysis hiring of generator 62.5 KVA

0 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)