why their is need of production version
Answers were Sorted based on User's Feedback
Answer / rasika deshpande
In production version, we assign the BOM and ROUTING
combination. And in case of alternate BOMs , it clears which
alternative bom has to be selected automatically.
Is This Answer Correct ? | 18 Yes | 1 No |
Answer / bharathish
Production version is a combination of BOM and Master
Recipe..which determines the production method means which
combination of BOM & Routing needs to be selected is
determined by production version...
Is This Answer Correct ? | 6 Yes | 1 No |
Answer / lalitshelare
Yes exactly it is correct.
thanks rasika as u posted the answer.
lalit
Is This Answer Correct ? | 4 Yes | 0 No |
Answer / varun jalota
One more important thing that we cant forget is that
Production Version also plays a very important roll in Lot
Sizing and Validity
In addition with above explain like interlinking with BOM
Alternate BOM and Routing.
Is This Answer Correct ? | 3 Yes | 0 No |
Answer / louis
Production versions is also used when:
- Routings; more than one Production line is used (with
different Costs),
- Alternative BOM's: is used to produce the same Finished
product, Example: in Pharmacutical 2 different chemicals
can be used to manufacture "Disprin's" etc.
*** It is defined in the Material Master & Production
Order.
Is This Answer Correct ? | 1 Yes | 1 No |
Answer / gobinath r
Production Version:
Alternative Routing with alternative BOM selected upon the
lotsize for better production efficency.for example the
company may have different production methods for different
lot size produced.
Is This Answer Correct ? | 0 Yes | 0 No |
Answer / shahid hussain
Beside all above answers I would add following:
It helps Standard Cost Estimate to be maintained on a
selected BOM and Routing (Production Version), can be fixed
in Material Master Costing 1 Tab
It Helps Planning for MRP to maintain the quota arrangement
for procurement proposals which is important for supply
chain planning and execution
Also help to avoid change/delete your master data (BOM
Routing etc) by controlling it through production versions
validity depending on
Lot Size
Validity Date
Help to have production planning by means of using line loading
Also help for mix costing ratios on mix costing scenario
Is This Answer Correct ? | 0 Yes | 0 No |
What is the use of stock requirement list?
Product Costing Run is over. Now If I add one more rawmaterial for that material also it has to included & run the cost. But it is not happening?
How is the processing time calculated in a wc when both labor, machine categories exist?
You want to integrate pp with fico. What steps would you take?
What are some important tables used in pp (production planning)?
What is a ‘routing’ in pp?
1000 pieces you run mrp on that time use md02 or md01
What is Material status and which view of the material master it is available?
What is the transaction code to run MRP for sales order?
How can you get planned orders scheduled so that you can do capacity leveling ?
Which BOM item category you have used?
After doing realization how we will check whether it is working or not?