why their is need of production version

Answer Posted / gobinath r

Production Version:

Alternative Routing with alternative BOM selected upon the
lotsize for better production efficency.for example the
company may have different production methods for different
lot size produced.

Is This Answer Correct ?    0 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

SPRO path for order, confirmation or requirement class.

2251


We have two storage locations are ‘0001’ and ‘0600’. Default storage location in process order is always ‘0001’ what determines this default location?

782


What is mrp group and what is the use of it?

629


What is plm (product lifecycle management) in sap pp?

597


What is the use of infogroups?

608






Difference between different strategy groups.

1087


Which tool you are using

1363


what are the settings needed for variant configuration?

1450


What are the customer activities followed for pp module ?

608


What is alternative BOM, or diff between BOM group and Group BOM?

1184


What are the key fields in MRP views?

1749


How is indian slab and us slab?

637


Standard mrp steps

1411


What is MTS and MTO and the difference between them?

1939


What is a ‘routing’ in pp?

654