how to find the carpenter work per day? how many cubic feet
they should be work per day?
Answers were Sorted based on User's Feedback
Answer / girish rawat
ON AN AVERAGE 1 CARPENTER I SEMI SKILLED CARPENTER AND 1
HELPER WITH GIVE YOU AN OUTPUT OF 10 TO 12 M2 OF SHUTTERING.
IT DECREASES IF YOU ARE FIXING BEAM BOTTOM OR STEP FOOTING.
IT INCREASES DURING COLUMN FIXING AND SLAB DECK SHUTTERING.
Is This Answer Correct ? | 45 Yes | 3 No |
Answer / md.sami
door,window work comes under furniture carpenter, if you ask wooden carpenter no will get you
Is This Answer Correct ? | 1 Yes | 0 No |
Answer / geethu
i hav asked about wood carpenter output?(doors,windows)
Is This Answer Correct ? | 0 Yes | 3 No |
Answer / harish
average one carpenter one helper they give out put of 12-
14m2of shuutering
Is This Answer Correct ? | 4 Yes | 10 No |
Difference between Statics, Dynamics, Kinetics, Kinematics
how to calculate cost for MS plate shuttering (show calculation/assumptions)
Unit weight of brick? Sand? Aggregate? Steel? Cement? Water?
28 Answers Aliens Group, Cemplex, DLF, L&T, LBC, Power Trade Engineering, Vishnu, VKM,
how many type of pipe using in plumbing?
What is the basic difference between OPC
How to calculate per inch area in a circle?(Dia is 2.17m)
wat is meant by aerocon bricks?
what is civil engineer greatest strength and weakness?
What is meant by Friction Pile?
please give me the rates of RCC(CUM), PCC(CUM), Brick Work(CUM), Tile Flooring, Saria Shuttering
37.18kg/qu.cm.Compressive Strength and 10.20% Water Absorption weight,Efflorescence-nil this result use in construction work
What is bending moment