Answer / faizan

If the VCB having the facility of UVT (Under voltage Trip)
then the VCB turn off automatically other vise it will
remains in ON condition if not.

Is This Answer Correct ?    7 Yes 0 No

If the 11 KV supply is fail. what will happened with it's breaker if it is supplay to the 11K..

Answer / sandipan

11KV motor'breaker will be tripped in U/V automatically

Is This Answer Correct ?    5 Yes 2 No

If the 11 KV supply is fail. what will happened with it's breaker if it is supplay to the 11K..

Answer / asad durez

if the any supply is fail not only 11 kv then the C.B will
remain in his on position.

Is This Answer Correct ?    1 Yes 0 No

Post New Answer

More Electrical Engineering Interview Questions

why the motor running in delta connection ? it can be in star?

13 Answers   NTPC,


its Kva and Kv are same?

3 Answers  


What safety followup during kWh meter isolation

0 Answers  


what is a,b,c,d checks diesel generator?

1 Answers   AFMC,


Why the magneti fields are not passes from southpole to north pole

0 Answers   SGML,






Instead of single phase(220), if we apply Phase to phase (R&Y)supply (eg: for lighting fixture). what will be the power formula?

1 Answers  


How to calculate the copper in HT motors if KW, RPM & Voltage is given

0 Answers   Control Dynamics, NTPC,


how one can design armature winding bothh front and back connection

1 Answers  


which connection is safer series or parallel?usually which connection we prefer at home?

5 Answers  


how wud i know that whether i have to use unitized package substation or transformer?

1 Answers  


What is the count of hvdc transmission lines in india?

0 Answers  


A single line diagram(SLD) and a purchase order of a 11/66kV switchyard of a power plant was given. In the SLD, only one lightning arrestor(LA) was shown, but the purchase order had need of 3 LAs. Is this correct, if yes, why?

2 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)