what is version 1

Answers were Sorted based on User's Feedback



what is version 1..

Answer / glamorous

Version One Enterprise: Process Overview

In Version One, there are five stages to planning and
executing projects: Product Planning, Release Planning,
Sprint Planning, Sprint Tracking, and Review. For smaller
projects it is possible to skip the Release Planning stage
completely.

In Product Planning the team composes, estimates, and
prioritizes Backlog Items. Once a product backlog exists,
the Product Owner has the option of organizing these
Backlog Items into one or more Releases. Within a Release,
Backlog Items are further organized into Sprints. During
Sprint Planning's detailed planning session, the team
defines the acceptance tests and identifies all tasks for
each Backlog Item in the Sprint.

Once the team completes all tasks for a Backlog Item and
all tests pass, the Product Owner accepts the Backlog Item.
Some teams choose to close the Backlog Item at this point
as well. At the end of the Sprint, the team closes the
Sprint and conducts a Retrospective. The process repeats
for the next Sprint.

Is This Answer Correct ?    1 Yes 0 No

what is version 1..

Answer / glamorous

 My Home:

1. Getting Started:

a. Getting Started: Below (table1) opens when we click
on this
The Getting Started page provides a new user
with a quick overview of the common actions performed in
the application. Click on an activity to see a list of
specific steps to perform it within Version One.

Additional resources available to all users
are also displayed to help new users learn about all the
assistance available in getting started with Version One.

Table1:
Table1: Common Activities

1. Enter A Backlog Item
2. Update Task/Test Progress
3. View My Work
4. Get New Work
5. Create A Sprint
6. View Sprint Progress
7. View Overall Process Steps

( Here it shows the description how can we open that step)
such as select Enter A Backlog Item in the common
activities then the respective steps shown in this pane)
1. Select a Project from the Left Navigation.
2. Select Backlog Item from the "Add New" Dropdown in
the Left Navigation.
3. Enter Backlog Item Title and Other Desired
Information.
4. Click "OK" in the Upper Right Corner
Go There (this is a hyperlink under each one if we click
then we can shift to that window)
Update Task/Test Progress
1. Select My Home, My Work Tab.
2. Update Task/Test Status if appropriate.
3. Enter Time Spent on the Task/Test in the Effort
Column (if available).
4. Update remaining To Do estimate.
5. Select "Apply".
View My Work
1. Select a Project from the Left Navigation.
2. Select My Home, My Work Tab.
3. All Your Backlog Items, Defects, Tasks, and Tests
will Appear in Workitem Summary.
Go There
Get New Work
1. Select a Project from the Left Navigation.
2. Go to the Sprint Tracking Section,
3. Taskboard Tab, and
4. Select (Nobody) from the Highlight Owner Dropdown.
5. Select the highest Priority Task that does not have
an Owner.
6. Click the upper right corner of the Task card and
select "Assign".
Create A Sprint
1. Select a Project from the Left Navigation.
2. Go to the Sprint Planning Section,
3. Sprint Scheduling Tab.
4. Click the "Add Sprint" Link
View Sprint Progress
1. Select a Project from the Left Navigation.
2. Select Reports in the main menu.
3. On the Reports Overview page, select Sprint
Dashboard under Sprint Reports.
4. Select the appropriate Sprint.
5. Click on 'Go' to run the report
View Overall Process
1. Go to the My Home Section,
2. Getting Started Tab, and Select Planning Overview.

Is This Answer Correct ?    1 Yes 0 No

what is version 1..

Answer / eswar

thanks for u answer 1

Is This Answer Correct ?    0 Yes 0 No

what is version 1..

Answer / glamorous

3) b. Planning Overview:

Here we have a chart of showing the functionality
of each and every phase
1. Product Planning:
Capture Backlog items
Estimate Backlog items
Prioritize Backlog items

2. Release Planning:
Define Release Projects
Schedule Backlog items
Assign Backlog to Teams

3. Sprint Planning
Setup Sprints
Select Backlog items
Define Tests
Identify Tasks

4. Sprint Tracking
Complete Tasks
Pass Tests
Accept Backlog items
Fix Defects

5. Review
Close Backlog items
Close Sprint
Conduct Retrospective

Is This Answer Correct ?    0 Yes 0 No

what is version 1..

Answer / eswar

thanks for answer 2

Is This Answer Correct ?    0 Yes 0 No

what is version 1..

Answer / eswar

thanks for answer 3

Is This Answer Correct ?    0 Yes 0 No

what is version 1..

Answer / glamorous

hello eswar through this the figures are not pasting so i
will send the document later for this so do ur work and
post any other questions













































Backlog Items and Defects Add Backlog
Item






Filter



Move to Project


1-10 of 10

Apply


Reset









Title ID Owner Priority Estimate
Project


Record problem onset date
B-01014
Justin
Medium


Team 1 CCHIT
Edit




Record problem chronicity
B-01015
Justin
Medium


Team 1 CCHIT
Edit




Track patient history
B-01016
Justin
Medium


Team 1 CCHIT
Edit




Track active and inactive problems
B-01017
Justin
Medium


Team 1 CCHIT
Edit




Show patient has completed advance directives
B-01018
Justin
Medium


Team 1 CCHIT
Edit




Show Continuity of Care Documents (CCD)
B-01019
Justin
Medium


Team 1 CCHIT
Edit




Allow users to review advance directives
B-01020
Justin
Medium


Team 1 CCHIT
Edit




Show when advance directives were reviewed
B-01021
Justin
Medium


Team 1 CCHIT
Edit




Create Continuity of Care Documents (CCD) for allergy and
medication history
B-01036
Justin
Medium


Team 1 CCHIT
Edit




Track patient history
B-01063



Team 1 CCHIT
Edit



Move to Project


1-10 of 10

Apply


Reset

Is This Answer Correct ?    0 Yes 0 No

what is version 1..

Answer / eswar

ok glamarous madam, ok i find and send the questions o

Is This Answer Correct ?    0 Yes 0 No

what is version 1..

Answer / glamorous

OK I FOUND A WEBSIT EFOR THE VERSION ONE
http://www.versionone.com/products_V1Enterprise_ReleasePlann
ing.asp OPEN AND ENJOY I WILL EXPLAIN U LATER OK I THINK
THIS IS THE BEST WEBSITE TO CLARIFY OUR DOUBTS RIGHT



THANKS FOR ALLINTERVIEW.COM

Is This Answer Correct ?    0 Yes 0 No

what is version 1..

Answer / eswar

i opened & verified thank madam

THANKS FOR ALLINTERVIEW.COM

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More Manual Testing Interview Questions

hi.i joined in a software testing course recently.but i dnt knw 'c' or 'c++',would it mind? my stream is ece. so i just had a C&DS IN OUR 1ST SEMESTER.

1 Answers  


What is ecp (equivalence class partition)?

0 Answers  


What is Bug Validation? What can be a different resultant after the same?

3 Answers   Satyam,


What if the application has functionality that wasn't in the requirements?

1 Answers   IBM,


what is cause effect graph?

2 Answers   Infosys,






Apart from testing what are ypur roles as a tester.

0 Answers  


what is the testing process followed in your company?

6 Answers   Mantra Group,


Does we make documentation for all defects?

2 Answers  


wat kinds of documents requied during regression testion ? at time regression testing is done? can we do it repeatdly

2 Answers  


is it not possible to automate full project??what r the parts in project that cant be automated(tht has to be done manually)?

0 Answers  


i m going to pay for air reservation online and i m paying through credit card supose i give credit card no 123456.how u chk this is valid or not.wat validation u put for kind of fields

2 Answers   informatics,


3. A bug report is a: a. A collection of independent, reusable test cases. b. A technical document that describes the various symptoms or failure modes associated with a single bug. c. A deliverable that details the strategic approach to a testing effort d. A & B

0 Answers  


Categories