How a project is made and deliverd to client? please put all
detailed steps internally?
Answers were Sorted based on User's Feedback
A Project as awhole from inception to Delivery is an Eight
Step Process. Broadly they are
Proposing , Planning, analysing, Designing, Building,
Testing, Implementing, Maintainenece
In Brief Proposing is a Four step Process, Defining initial
Planning document with subheads of Introduction, Business
Proble,Current Tech Environment and Technical Architecture.
Then comes Palnning with almost 6 subheads: Define the
scope , Business Oppurtunity, Indetify stake Holeder
requirements , Scope constraints, Sponsor , Indetify
Project Team and Develop a Plan.
Analysing is what is broadly into Business flow,
constraints
Designing is four step Intial design with expert review
followed by Detailed Design and review.
Building includes H/W environment, Security, Tech Arch
etc.......
Testing - Unit testing followed by Integrating test and
system tests.
Implelemting and Maintanace
| Is This Answer Correct ? | 36 Yes | 7 No |
Answer / shri
Initiating, planning, executing and controling and closure
of project.
| Is This Answer Correct ? | 4 Yes | 2 No |
You are a project manager for Candy Works candy factory. Your project involves reporting information from the newly installed candy-counting machine to the financial system. This will give executives the ability to see production run counts at any rime during the day. The project sponsor has promised you a bonus if you get this project completed two weeks sooner than the scheduled project end date. The bonus will come in handy on your trip to the Bahamas planned for later this spring. You've got a few remaining project activities to wrap up before you can close out the project. Which of the following is the most appropriate response? A. You tell the sponsor the project is complete and treat the remaining activities as though they're problems that came up after project closure so that you can still get the bonus. B. You tell the sponsor the remaining activities are outside the scope of the project so the project really is completed and collect your bonus. C. You tell the sponsor the stakeholders added these requirements after the project was well under way and you never agreed to include them in the project so the project really is complete, and you collect your bonus. D. You tell the sponsor you aren't going to make the two-week early completion date as there are remaining activities to finish up.
What is the difference between contingency and mitigation plan?
The Critical Path Method is a mathematical tool and technique of the Schedule Development process. All of the following are true regarding CPM except: A. Determines a single early and late start date and a single early and late finish date B. Calculates expected value C. Focuses on the calculation of float time D. Shows the critical path, or the path with the longest duration
Your project sponsor has requested a cost estimate for the project you're working on. This project is similar in scope to a project you worked on last year. She would like to get the cost estimates as soon as possible. Accuracy is not her primary concern right now. She needs a ball park figure by tomorrow. You decide to use: A. Analogous estimating techniques B. Bottom-up estimating techniques C. Parametric modeling techniques D. Computerized modeling techniques
You are project manager for an engineering company. Your company won the bid to add ramp-metering lights to several on-ramps along a stretch of highway at the south end of the city. You subcontracted a portion of the project to another company. The subcontractor's work involves digging the holes and setting the lamp poles in concrete. The subcontractor's performance is not meeting the contract requirements. All of the following are valid options except: A. You document the poor performance in written form and send the correspondence to the subcontractor change request through Contract Administration. B. You terminate the contract for poor performance and submit a change request through Contract Administration. C. You submit a change request through Contract Administration to ask the subcontractor to comply with the terms of the contract. D. You agree to meet with the subcontractor to see if a satisfactory solution can be reached.
What are the tools and techniques of the Quantitative Risk Analysis process? A. Checklists, flowcharting, interviewing B. Interviewing, sensitivity analysis, decision tree analysis, simulation C. Checklists, sensitivity analysis, decision tree analysis, information-gathering techniques D. Interviewing, checklists, assumptions analysis, risk probability impact
You are a project manager for a manufacturing firm that produces Civil War-era replicas and memorabilia. You discover a design error during a test production run on your latest project. Which of the following is the most likely response to this problem? A. Reduce the technical requirements so that the error is no longer valid. B. Go forward with production and ignore the error. C. Go forward with production but inform the customer of the problem. D. Develop alternative solutions to address the error.
What are the csfs in the software project management ?
You are a project manager for Move It Now trucking company. Your company specializes in moving household goods across the city or across the country. Your project involves upgrading the nationwide computer network for the company. Your lead engineer has given you the following estimates for a critical path activity: 60 days most likely, 72 days pessimistic, 48 days optimistic. What is the expected value, or weighted average? A. 54 B. 66 C. 60 D. 30
All of the following are characteristics of the project Closing processes except: A. Probability for success is greatest here. B. The project manager's influence is greatest here. C. The stakeholders' influence is least here. D. Risk is greatest here.
You have been assigned to a project that will allow job seekers to fill out applications and submit them via the company website. You report to the VP of human resources. You are also responsible for screening applications for the information technology division and setting up interviews. The project coordinator has asked for the latest version of your changes to the online application page for his review. Which organizational structure do you work in? A. Functional organization B. Weak matrix organization C. Projectized organization D. Balanced matrix organization
You are a project manager for Giraffe Enterprises. You've recently taken over for a project manager who lied about his PMI certification and was subsequently fired. Unfortunately, he did a poor job of Scope Definition. You know if you don't correct this, one of the following could happen: A. The stakeholders will require overtime from the project team to keep the project on schedule. B. The WBS will adversely affect the deliverable breakdowns, and costs will increase. C. The scope management plan will require changes. D. The project costs could increase, there might be rework, and schedule delays may result.