You are developing your project schedule and have decided to use the PERT method to determine project duration. The estimates you've gathered so far include the following: Most likely is 200 hours, optimistic is 180 hours, and pessimistic is 220 hours. Which of the following is the correct PERT estimate?
A. 190
B. 266
C. 200
D. 210
No Answer is Posted For this Question
Be the First to Post Answer
The project schedule is used to determine all of the following except: A. Cost estimates B. Activity start dates C. Float times D. Activity end dates
You are working on a project to develop a new website for your company. You are monitoring results of the project to determine if they comply with standards set out during the Planning processes. You are also taking steps to eliminate unsatisfactory results. This might mean rework in some cases. Which process are you in? A. Risk Monitoring and Control B. Quality Control C. Integrated Change Control E. Scope Change Control
Your project was just completed. Due to some unfortunate circumstances, the project was delayed causing cost overruns at the end of the project. This information might be useful on future projects in all of the following activities except: A. Cost estimating B. Allocating resources C. Product verification D. Activity estimating
define the zero date in project management
You are the project manager for Heartthrobs by the Numbers Dating Services. You’re working on an updated Internet site that will display pictures as well as short bios of prospective heartbreakers. You have your activity list and resource requirements in hand and are planning on using qualitatively based durations and reserve time to determine activity durations. Which of the following is true? A. You are using inputs of the Activity Duration Estimating process. B. You are using tools and techniques of the Cost Estimating process. C. You are using tools and techniques of the Activity Duration Estimating process. D. You are using inputs of the Cost Estimating process.
You are constructing a probability/impact risk rating matrix for your project. Which of the following is true? A. The PI matrix multiplies the risk's probability by the cost of the impact to determine an expected value of the risk event. B. The PI matrix multiplies the risk's probability scales, which fall between 0.0 and 1.0, and the risk’s impact scales to determine a risk score. C. The PI matrix multiplies the risk's probability by the expected value of the risk event to determine the risk impact and assign a risk score based on a predetermined threshold. D. The PI matrix multiplies the risk's probability scales and the risk's impact scales, which fall between 0.0 and 1.0, to determine a risk
You are the project manager working on a research project for a new drug treatment. Your preliminary project schedule runs past the due date for a federal grant application. The manager of the R&D department has agreed to release two resources to work on your project in order to meet the federal grant application date. This is an example of: A. Crashing B. Fast trucking C. Resource leveling D. Adjusting the resource calendar
You know that BAC = 375, PV = 300, AC = 200, and EV = 250. Variances that have occurred on the project to date are not expected to continue. What is the ETC? A. 75 B. 50 C. 125 D. 150
The lowest level of the WBS is called what? A. Code of accounts B. Requirement C. Milestone D. Work package
explain the contents of menubar
As a project manager, you know that the most important activity to ensure customer and stakeholder satisfaction is which of the following: A. Documenting the requirements B. Documenting the performance measurements C. Reporting changes and updating the project plan and other project documents where appropriate D. Reporting project status timely and regularly
Your project's primary constraint is quality. In order to make certain the project team members don't feel too pressed for time and to avoid schedule risk, you decide to use which of the following activity estimating tools? A. Expert judgment B. Quantitatively based durations C. Reserve time D. Analogous estimating