You are developing your project schedule and have decided to use the PERT method to determine project duration. The estimates you've gathered so far include the following: Most likely is 200 hours, optimistic is 180 hours, and pessimistic is 220 hours. Which of the following is the correct PERT estimate?
A. 190
B. 266
C. 200
D. 210


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

How do you communicate bad news in your team?

0 Answers  


As a project manager, you know that the most important activity to ensure customer and stakeholder satisfaction is which of the following: A. Documenting the requirements B. Documenting the performance measurements C. Reporting changes and updating the project plan and other project documents where appropriate D. Reporting project status timely and regularly

0 Answers  


All of the following are true regarding configuration management except: A. Requires all acceptance decisions to be made through the CCB B. Serves as a change control system C. Describes the physical characteristics of the product of the project D. Controls changes to the characteristics of an item or system

0 Answers  


Sally is a project manager working on the Resource Planning process. She should consider all of the following when developing the resource requirements output except: A. WBS B. Supply purchase policies C. Resource rates D. Special knowledge and talents

0 Answers  


You are a fabulous project manager, and your team thinks highly of you. You are well respected by the stakeholders, management ream, and project team. When you make decisions, others follow your lead as a result of which of the following? A. Referent power B. Expert power C. Legitimate power D. Punishment power

0 Answers  






You are a project manager for Candy Works candy factory. Your project involves reporting information from the newly installed candy-counting machine to the financial system. This will give executives the ability to see production run counts at any rime during the day. The project sponsor has promised you a bonus if you get this project completed two weeks sooner than the scheduled project end date. The bonus will come in handy on your trip to the Bahamas planned for later this spring. You've got a few remaining project activities to wrap up before you can close out the project. Which of the following is the most appropriate response? A. You tell the sponsor the project is complete and treat the remaining activities as though they're problems that came up after project closure so that you can still get the bonus. B. You tell the sponsor the remaining activities are outside the scope of the project so the project really is completed and collect your bonus. C. You tell the sponsor the stakeholders added these requirements after the project was well under way and you never agreed to include them in the project so the project really is complete, and you collect your bonus. D. You tell the sponsor you aren't going to make the two-week early completion date as there are remaining activities to finish up.

0 Answers  


how to handle project single handed?and what are the roles and responsibilities of a project leader?

4 Answers   Areva,


You are a project manager for an engineering company. Your company won the bid to add ramp-metering lights to several on-ramps along a stretch of highway at the south end of the city. You subcontracted a portion of the project to another company. The subcontractor's work involves digging the holes and setting the lamp poles in concrete. The subcontractor's performance is not meeting the contract requirements, because the poles are not buried to the correct depth. Which of the following is true? A. You are in the Quality Assurance process and have performed a quality audit to assure correctness of work. B. You are in the Scope Verification process and have performed a quality audit to assure correctness of work. C. You are in the Contract Administration process and have completed a contract audit to assure the subcontractor's performance meets the contract requirements. D. You are in the Performance Reporting process and have completed a performance review of the contractor's work.

0 Answers  


Your selection committee meets on a semiannual basis. They've determined that projects must meet or exceed a specific profit limit in order to be accepted and prioritized on the project list. Which of the following is true? A. The selection committee has defined project selection criteria, which is a tool and technique of Initiation. B. The selection committee has defined project selection methods, which is a tool and technique of Initiation. C. The selection committee has defined project selection methods, which is an input to Initiation. D. The selection committee has defined project selection criteria, which is an input to Initiation.

0 Answers  


You are a project manager for Move It Now trucking company. Your company specializes in moving household goods across the city or across the country. Your project involves upgrading the nationwide computer network for the company. Your lead engineer has given you the following estimates for a critical path activity: 60 days most likely, 72 days pessimistic, 48 days optimistic. What is the standard deviation? A. 22 B. 20 C. 2 D. 4

0 Answers  


You are constructing a probability/impact risk rating matrix for your project. Which of the following is true? A. The PI matrix multiplies the risk's probability by the cost of the impact to determine an expected value of the risk event. B. The PI matrix multiplies the risk's probability scales, which fall between 0.0 and 1.0, and the risk’s impact scales to determine a risk score. C. The PI matrix multiplies the risk's probability by the expected value of the risk event to determine the risk impact and assign a risk score based on a predetermined threshold. D. The PI matrix multiplies the risk's probability scales and the risk's impact scales, which fall between 0.0 and 1.0, to determine a risk

0 Answers  


You are the project manager for BB Tops, a nationwide toy store chain. You are working on estimates for your latest project and have gathered several variables for your model. You've determined the following: A. Parametric modeling is a top-down technique that uses variables to produce time estimates. B. Parametric modeling is a mathematical formula that uses variables to produce cost estimates. C. Contingency estimating is a top-down technique that uses variables to produce cost estimates. D. Contingency estimating is a mathematical model that uses variables to produce time estimates.

0 Answers  


Categories