What is your leadership style?



What is your leadership style?..

Answer / arindom borah

I believe that a manager cannot and should not be defined by his or her leadership style. The leadership style has to change as per the situation which is to be managed. It's not very easy. By nature, I am a soft spoken person.But in certain situations and/or with certain individuals, if the aggressive style is necessary,I can be more aggressive than anyone else,and I won't be acting, the emotions will be genuine. That's why its hard. Acting is easy and people also can see through you easily.

Is This Answer Correct ?    4 Yes 6 No

Post New Answer

More Project Management Interview Questions

You are the project manager for an outdoor concert event scheduled for 1 year from today. You're working on the procurement plan for the computer software program that will control the lighting and screen projections during the concert. You've decided to contract with a professional services company that specializes in writing custom software programs. You want to minimize the risk to the organization, so you'll option for which contract type? A. Fixed price plus incentive B. Cost plus fixed fee C. Fixed price D. Cost plus incentive

1 Answers  


Which of the following is true? A. Discounted cash flow analysis is the least precise of the cash flow techniques as it does not consider the time value of money. B. NPV is the least precise of the cash flow analysis techniques as it assumes reinvestment at the discount rate. C. Payback period is the least precise of the cash flow analysis techniques as it does not consider the time value of money. D. IRR is the least precise of the cash flow analysis techniques because it assumes reinvestment at the cost of capital.

1 Answers  


Project managers have the highest level of authority and the most power in which type of organizational structure? A. Projectized B. Strong matrix C. Functional D. Balanced matrix

1 Answers  


How do you handle change request?

1 Answers  


You are going to take some performance measurements for your current project. You know that PV = 450, AC = 500, and EV = 375. What is the CV and SV respectively? A. CV = 125, and SV = 75 B. CV=-75, and SV=-125 C. CV = 75, and SV = 125 D. CV=-125, and SV=-75

1 Answers  


You are going to lake some performance measurements for your current project. You know that PV = 450, AC = 500, and EV= 375. What is the CPI and SPI respectively? A. CPI = .90, and SPI = 1.2. B. CPI = .75, and SPI = .83. C. CPI = 1.2, and SPI = .90. D. CPI = .83, and SPI = .75.

1 Answers  


You are a project manager for Picture Shades, Inc. They manufacture window shades for hotel chains that have replicas of Renaissance-era paintings on the inside of the shades. Picture Shades is taking their product to the home market, and you're managing the new project. They will offer their products at retail stores as well as on their website. You're developing the project schedule for this undertaking and have determined the critical path. Which of the following is true? A. You calculated the most likely start date and most likely finish dates, float time, and weighted average estimates. B. You calculated the activity dependency, and the optimistic and pessimistic activity duration estimates. C. You calculated the early and late start dates, early and late finish dates, and float times for all activities. D. You calculated the optimistic, pessimistic, and most likely duration times and the float times for all activities.

1 Answers  


Your selection committee is debating between two projects. Project A has a payback period of 18 months. Project B has a cost of $125,000 with expected cash inflows of $50,000 the first year and $25,000 per quarter after that. Which project should you recommend? A. Either Project A or Project B because the payback periods are equal B. Project A because Project B's payback period is 21 months C. Project A because Project B's payback period is 24 months D. Project A because Project B's payback period is 20 months

1 Answers  


What do you think you can bring to this position?

1 Answers   Ross Stores, Starbucks,


You are the project manager for a top-secret software project for an agency of the United States Government. Your mission, should you choose to accept it, is to complete the project using internal resources. The reason is because getting top secret clearances for contractors takes quite a bit of time and waiting for clearances would jeopardize the implementation date. Your programmers are 80 percent of the way through the programming and testing work when your agency appoints a new executive director. Slowly but surely your programmers are taken off this project and reassigned to the executive director's hot new project. Which of the following type of project ending is this? A. Starvation B. Extinction C. Addition D. Integration

1 Answers  


What is the difference between risk impact and risk probability?

1 Answers  


You are a contract project manager working with the State of Bliss. Your latest project involves rewriting the Department of Revenue's income tax system. As project manager, you have taken all the appropriate actions regarding confidentiality of data. One of the key stakeholders is a huge movie huff, and she has the power to promote you into a better position at the conclusion of this project. She's reviewing some report data that just happens to include confidential information regarding one of her favorite movie superstars. What is the most appropriate response? A. Report her to the management team. B. Request that she immediately return the information, citing conflict of interest and violation of confidential company data. C. Do nothing as she has the proper level of access rights to the data and this information showed up unintentionally. D. Request that she immediately return the information until you can confirm that she has the proper level of access rights to the data.

1 Answers  


Categories