Which of the following is true regarding Administrative Closure?
A. It occurs at the end of a project phase and at the end of the project.
B. It occurs at the end of the project phase only.
C. It occurs at the end of the project only.
D. It is performed prior to Contract Closeout.



Which of the following is true regarding Administrative Closure? A. It occurs at the end of a proj..

Answer / Somraj Dheeman

A. It occurs at the end of a project phase and at the end of the project.

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More Project Management Interview Questions

You work for a large manufacturing plant. You're working on a new project for an overseas product release. This is the company's first experience in the overseas market, and they hope to make a big splash with the introduction of this product. The project entails producing your product in a concentrated formula and packaging it in smaller containers than the U.S. product uses. A new machine is needed in order to mix the first set of ingredients in the concentrated formula. Which of the following is true? A. The new machine, the concentrated formula, and the smaller package are each project constraints. B. The new machine, the concentrated formula, and the smaller package description must be incorporated into the product description document. C. The new machine, the concentrated formula, and the smaller package are each project assumptions. D. The new machine, the concentrated formula, and the smaller package are each considered deliverables.

1 Answers  


Procurement audits review what? A. The procurement process from Procurement Planning through Contract Administration B. The contract administration process from Solicitation Planning through Contract Administration C. The procurement process from Procurement Planning through Contract Closeout D. The contract administration process from Solicitation Planning through Contract Closeout

1 Answers  


You are a project manager for Dutch Harbor Consulting. Your latest project involved the upgrade of an organization's operating system on 236 servers. You performed this project under contract. You are in the Contract Closeout process and know that you should document: A. Lessons learned B. Performance measurements C. Formal acceptance D. Product verification

1 Answers  


You are a project manager working for Mail House King. Your company processes orders for several mail-order catalog companies. Your project is to install new mail-sorting equipment and software. You’ve had some problems and experienced some variances so far during the project. You do not expect these variances to continue, as they're atypical. Your project sponsor has asked for an EAC. You know the following information: PV = 800, BAC = 700, EV = 675, AC = 750, and ETC = 30. Which of the following is the correct EAC given the circumstances? A. 25 B. 760 C. 775 D. 833

1 Answers  


You are a project manager for a telecommunications firm. You're working on a project that entails upgrading technical hardware and equipment. The estimated cost of the hardware and equipment is $1,725,000. You are reviewing products from three different vendors. One of the vendors invites you to lunch. What is the most appropriate response? A. Thank them but let them know this could be a conflict of interest since you haven't made a decision about which vendor you're going to choose. B. Thank them and decline. You know this could be considered personal gain, which could call your integrity into question. C. Thank them and accept. You don't believe there is a conflict of interest or a personal integrity issue. D. Thank them and decline. You believe this could be a conflict of interest on the part of the vendor, and you don't want to encourage that behavior.

1 Answers  


You are the project manager for Rivera Gourmet Adventure Vacations. Rivera combines the wonderful tastes of great gourmet food with outdoor adventure activities. Your project involves installing a new human resources software system. Jason, the database analyst working on this project, is over allocated. Which of the following is true? A. You should use resource requirements updates to determine availability and smooth out resource over allocation. B. You should use crashing to resource level the critical path tasks. C. You should use resource leveling heuristics to smooth out resource assignments. D. You should use fast tracking to resource level the critical path tasks.

1 Answers  


You work for a large manufacturing plant. You're in the Initiation process of a new project for an overseas product release. This is the company's first experience in the overseas market, and they hope to make a big splash with the introduction of this product. The project entails producing your product in a concentrated formula and packaging it in smaller containers than the U.S. product uses. A new machine is needed in order to mix the first set of ingredients in the concentrated formula. Which of the following actions should the project manager take? A. The project manager should document the project's goals and known deliverables in a high-level overview document and recommend the project proceed. B. The project manager should document the project's goals and known deliverables in a high-level overview document and assume the project is a go. C. The project manager should document the project's goals and known deliverables in a high-level overview document and recommend a feasibility study be performed. D. The project manager should document the project's goals and known deliverables in a high-level overview document and deliver it to the stakeholders.

1 Answers  


During which project management process are risk and stakeholder's ability to influence project outcomes the highest at the beginning of the process? A. Planning B. Executing C. Initiation D. Controlling

1 Answers  


What are the different kinds of project management tools you worked with?

1 Answers  


Mathematical models using linear, dynamic, integer, or algorithm models are considered: A. Project selection criteria B. A form of expert judgment C. Project selection methods D. A form of historical information

1 Answers  


What is the key activity during Contract Closeout and Administrative Closure? A. Documenting lessons learned B. Creating project archives C. Disseminating information to formalize project closure D. Documenting project closure

1 Answers  


Your project depends on a key deliverable from a vendor you've used several times before with great success. You're counting on the delivery to arrive on June 1. This is an example of : A. Constraint B. Objective C. Assumption D. Goal

1 Answers  