Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


Integrity in the project management field is accomplished through all of the following except:
A. Training to learn how to manage relationships with others from different cultures
B. Adhering to an ethical code
C. Applying established project management processes
D. Following the Project Management Professional Code of Professional Conduct


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

You are the project manager for Heart of Texas casual clothing company. Your project involves installing a new human resources system. You've identified the risks associated with this project and are ready for the next step. What is the next step? A. You will evaluate the risks and assign probabilities and impacts using Qualitative and/or Quantitative Risk Analysis. B. You will use the Delphi technique to confirm the risks you've detailed and identify others you may have missed. C. You must evaluate the risks and assign probabilities and impacts using both Qualitative Risk Analysis, which comes first, then Quantitative Risk Analysis. D. You will define the steps to take to respond to the risks and detail them in the risk response plan.

0 Answers  


You are a project manager for Picture Shades, Inc. They manufacture window shades for hotel chains that have replicas of Renaissance-era paintings on the inside of the shades. Picture Shades is taking their product to the home market, and you're managing the new project. They will offer their products at retail stores as well as on their website. You're developing the project schedule for this undertaking and have determined the critical path. Which of the following is true? A. You calculated the most likely start date and most likely finish dates, float time, and weighted average estimates. B. You calculated the activity dependency, and the optimistic and pessimistic activity duration estimates. C. You calculated the early and late start dates, early and late finish dates, and float times for all activities. D. You calculated the optimistic, pessimistic, and most likely duration times and the float times for all activities.

0 Answers  


You are going to take some performance measurements for your current project. You know that PV = 450, AC = 500, and EV = 375. What is the CV and SV respectively? A. CV = 125, and SV = 75 B. CV=-75, and SV=-125 C. CV = 75, and SV = 125 D. CV=-125, and SV=-75

0 Answers  


Which of the following is true regarding IRR? A. IRR assumes reinvestment at the cost of capital. B. IRR is the discount rate when NPV is greater than zero. C. IRR is a constrained optimization method. D. IRR is the discount rate when NPV is equal to zero. ?

0 Answers  


Explain the difference between risk and issues?

0 Answers  


You are a project manager working on contract. You’ve performed earned value analysis and discovered that the project will be completed on time and under the original estimated amount. This means the profit to your company will decrease as will your personal bonus. Which of the following should you do? A. Add activities to the project to increase the cost enough to meet the original estimated amount. B. Tell the customer you're adding additional requirements to the project chat were originally cut because of cost constraints. C. Inform the customer that the project is completed and has come in under budget. D. Bill the customer for the full amount of the contract as this was the original agreed-upon price.

0 Answers  


How do you set goals for your team?

0 Answers  


You are a project manager for Move It Now trucking company. Your company specializes in moving household goods across the city or across the country. Your project involves upgrading the nationwide computer network for the company. Your lead engineer has given you the following estimates for a critical path activity: 60 days most likely, 72 days pessimistic, 48 days optimistic. What is the expected value, or weighted average? A. 54 B. 66 C. 60 D. 30

0 Answers  


How do you handle conflicts in the Team Management ?

0 Answers   Microsoft,


You are the project manager for a construction company that is building a new city and county office building in your city. Your CCB recently approved a scope change. You know that scope change might come about as a result of all of the following except: A. Schedule revisions B. Product scope change C. Changes to the agreed-upon WBS D. Changes to the project requirements

0 Answers  


What is the difference between project, program, and portfolio?

0 Answers  


Obtaining formal project plan approval and sign-off is important for all of the following reasons except: A. Stakeholders are able to recommend a project Planning methodology to follow throughout the remaining process groups. B. Stakeholders are aware of the project details, which make them more likely to participate in future project decisions. C. Stakeholders will be more likely to cooperate. D. Stakeholders are aware of the specific details regarding project schedules, budgets, and risks.

0 Answers  


Categories