what is entry and exit criteria?
Answers were Sorted based on User's Feedback
Answer / guest
Entry criteria: Before Integration criteria all unit test
cases should be passed and Unit testing should be completed.
Exit: When Integrated modules are working as per their
requirement and all integration test cases should be passed
without any critical/Major defects
| Is This Answer Correct ? | 5 Yes | 1 No |
unit testing output is entrylevel criteria for integration
testing.the same output is exit level criteria for unit
tsting.
| Is This Answer Correct ? | 1 Yes | 0 No |
Answer / madhubabu
Entry criteria: 1)first study the SRS document and
understand the current project.
2)test environment established.
3)receiving the software build from the
programmers
exit criteria: 1)all major bugs are executed.
2)all expected test cases are solved.
3)time exceeded.
4).all minor bugs are solved
| Is This Answer Correct ? | 1 Yes | 0 No |
Answer / suvarna
Entry and Exit criteria means
Entry includes Pre Conditions like SRS(Usecases, Activity
diagram, mockup screens & HLDD, LLDD.
Exit includes Post Conditions like Traceability matrix and
Sign off.
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / sandeep
Entry criteria start with R&A phase
Evaluating exit criteria has the following major tasks:
o Checking test logs against the exit criteria specified in
test planning.
o Assessing if more tests are needed or if the exit
criteria specified should be changed.
o Writing a test summary report for stakeholders.
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / suneel reddy
Entry criteria is nothing but how to approach particular
thing?
suppose in Test plan entry criteria is functional
description and exit criteria is approach
| Is This Answer Correct ? | 1 Yes | 4 No |
Why we do load and performance testing?
What is the Use of Bug Tracking Tools.? what are the common and Importent Fields in any Bug Tracking Tool?
Negative testcases for salary application..
can u explan me clearly wt is web based app: and client server app:
What is quality assurance?
How to start testing after project kick off ???
Suppose you find a bug in production, how would you make sure that the same bug is not introduced again?
Can anybody help me what is the diff between CMM,SEI,PCMM and six sigma?
What is Defect Density ? What is the formula? Explain with example
What are basic, core, practises for a QA specialist?
1.what ia QA and QC? 2.how do you configure qtp and testdirector? 3.IN Online banking syatem project Which functionalities of QTP your using? 4.how do you test the money transform from one account to another account?
How many levels of ISTQB Certifications r there? What r they? When they will be commenced?