Answer / rajesh ahirrao
For System Testing,Entry Criteria is-
1) SRD(S/W Req.Docs)should be freezed.
2) All Test Case writting should be completed,review.
3) Unit testing,Integration testing phase should be
completed.
Exit Criteria is -
1) All High Priority & HIgh Severioty defects should be
closed( fixed).
2) Application should be worked as per User's expectation.
3) Application should be meet successfully all the Users
requirements. etc..
Please suggest me if I am wrong...
Thanks,
Rajesh Ahirrao - (Hyderabad).
ahirrao.rajesh@gmai.com
| Is This Answer Correct ? | 15 Yes | 0 No |
Answer / harjeet kaur
Entry criteria for testing is as soon as SRS is prepared the
testing should be started. Exit criteria is decided by
either project manager or when the application starts
working normally.
| Is This Answer Correct ? | 9 Yes | 3 No |
Answer / kiranmayi
Entry and Exit criteria are defined by the company.In
general:
The Entry criteria are:
• The SIT code and environment shakedown was
successfully completed and there will be no interruptions
to the system test as a result of either
• Successful completion of unit testing and
integration tesing in development environment
• Updated Change Control Logs
Exit criteria are:
• All Requirements that are In Scope have been met
and the severity 1&2 variances are resolved.
Let me know if any questions
bommi_ki@yahoo.ca
| Is This Answer Correct ? | 1 Yes | 1 No |
why nds?
5 negative test case for lift....
5 Answers Deloitte, RBS, Wipro,
There is only requirements document. You have 10 days and 8 resources to release the system.At the end of the 8th day u tell ur TL that system is ready for release. How will you proceed with the testing process or in other words what all approach you will follow once you get requirements
How do u prepare test environment for ur application?
Hi friends I am kranti completed my IT diploma in 2005 & after that complete my software testing course. Now I am working in small software form as software tester. I have 2 + year experience in manual testing. Now I wan to change company. Plz told me is there any effect that I can not have any degree although I have 2 + experience ?
What is the diffrence between BUILD & RELEASE ?
Who can perform the unit testing?
when we swipe the credit card what will genertaed in Back end. how system will validated from the back end for credit card who is Aquriree and Issuer ,
What is quality center? What are the modules of quality center?
This is question is for system testing: What are Global catalog server, Schema Master and other NDTS roles ?
4 Answers AZTEC, HP, Symantec, Veritas,
What are the Major Functionality for a ATM machine ??
A defect posted by another tester, and it is fixed, and that fixed bug has come to you for testing, and you don't know the functionality, what do you do ?