Who fixes the bug as Severity and priority ?
Answers were Sorted based on User's Feedback
Answer / aashish
serverity is decided by test engineer
and priority is decide by project manager
| Is This Answer Correct ? | 3 Yes | 1 No |
Answer / reddy
It depends upon organization to organization. Anyone can
assign bug's severity and priority if he knows rules within
the project. Rules are decided mutually between
Developement and QA teams. You can find out with your team
member or your immediate boss about the practise. Generally
team lead will assign or modify the severity & priority of
the bug to avoid confusion.
| Is This Answer Correct ? | 2 Yes | 0 No |
Answer / karnati sreedhar
Severity Will be Fix by Test Engineer or Test Lead From
Testing Dept
Priority Will be Fix by Defect Tracking Team
Project Manager or Sr.From Developement Dept Or Sr.From
Testing Dept Or Some Times Client Also Fix the Bug(If the
Client is Familer with the Project)
| Is This Answer Correct ? | 2 Yes | 1 No |
Answer / senthilkumar
TEst leader only know how much that bug effect the
application...so he only assign sevearity status....
| Is This Answer Correct ? | 1 Yes | 0 No |
Answer / sunil
severity is set by tester.
priority is set by developer.
| Is This Answer Correct ? | 1 Yes | 0 No |
Answer / keshab
It depends entirely on the size of the company. Severity
tells us how bad the defect is. Priority tells us how soon
it is desired to fix the problem.
In some companies, the defect reporter sets the severity
and the triage team or product management sets the
priority. In a small company, or project (or product),
particularly where there aren't many defects to track, you
can expect you don't really need both since a high severity
defect is also a high priority defect. But in a large
company, and particularly where there are many defects,
using both is a form of risk management.
| Is This Answer Correct ? | 1 Yes | 1 No |
Answer / shrinivas poodari
Seviority is fixed by the project manager or test lead and
priority is fixed by the senior test engineer/test engineer
or if the "client" is famailier with the application then
that situations may client is also involved to fixed the
seviority and priority.
| Is This Answer Correct ? | 1 Yes | 2 No |
How can you optimize the Test Case.
What is regression testing? When to apply it?
What are the types of maintenance?
Usecases and nounlists are associated with the following Requirement analysis methodologies 1.Information engineering 2.Object oriented analysis 3.Structural analysis 4.Functional analysis.
wht is Defect removable efficiency
Which appraisal method class is the best?
comptability testing with ui means,any body can expain me how we perform compatability testing in real time,don;t give definetions
Give me different methodologies used in testing?
What are the different types of integration testing?
What is the difference between white box, black box, and gray box testing?
What is limitation of v shaped model
Meaning of Web Application. my doubt is www.yahoo.com .it is web application?