Which of the following is constraint chat you might find during the Organizational Planning process?
A. Organizational structure, expected staff assignments, collective bargaining agreements, and project management team preferences
B. Organizational structure, organizational interfaces, technical interfaces, and interpersonal interfaces
C. Organizational interfaces, expected staff assignments, collective bargaining agreements, and project management team preferences
D. Organizational interfaces, technical interfaces, and interpersonal interfaces
No Answer is Posted For this Question
Be the First to Post Answer
The project manager, stakeholders, and project team members all have roles and responsibilities throughout the project. As the project manager, you might link the project scope definition to the project roles and indicate which activities each person will participate in. You might display this information in which of the following ways: A. PDM B. RAM C. SOW D. RRM
what is a project management?
16 Answers Areva, GB Engineering, Proteans,
You are the project manager for a top-secret software project for an agency of the United States Government. Your mission, should you choose to accept it, is to complete the project using internal resources. The reason is because getting top secret clearances for contractors takes quite a bit of time and waiting for clearances would jeopardize the implementation date. Your programmers are 80 percent of the way through the programming and testing work when your agency appoints a new executive director. Slowly but surely your programmers are taken off this project and reassigned to the executive director's hot new project. Which of the following type of project ending is this? A. Starvation B. Extinction C. Addition D. Integration
You are the project manager for Lucky Stars Candies. You've identified the deliverables and requirements and documented them where? A. In the scope statement, which will be used as in input to the Scope Definition process B. In the scope definition document, which is used as an input to the Scope Planning process C. In the WBS, which is an output of the Scope Planning process D. In the WBS, which is a tool and technique of the Scope Definition process
Scope definition is necessary for all of the following reasons except: A. To subdivide project deliverables into smaller components B. To assess the stability of the project scope C. To facilitate time and cost estimates D. To facilitate responsibility and assignment
Mathematical models using linear, dynamic, integer, or algorithm models are considered: A. Project selection criteria B. A form of expert judgment C. Project selection methods D. A form of historical information
Which of the following is true regarding product descriptions? A. The product description is an output of the Initiation process. It describes the characteristics of the product or service. B. The product description is an output of the Initiation process. It describes the characteristics of the product or service and less detail in the early phases of the project. C. The product description is an input of the Initiation process. It describes the characteristics of the product or service and contains a lot of detail in the early phases of the project. D. The product description is an input of the Initiation process. It describes the characteristics of the product or service.
You have just prepared an RFP for release. Your project involves a substantial amount of contract work detailed in the RFP. Your favorite vendor drops by and offers to give you and your spouse the use of their company condo for your upcoming vacation. It's located in a beautiful resort community that happens to be one of your favorite places to go for a get away. What is the most appropriate response? A. Thank the vendor but decline the offer, as you know this could be considered a conflict of interest. B. Thank the vendor and accept. This vendor is always offering you incentives like this, so this offer does not likely have anything to do with the recent RFP release. C. Thank the vendor, accept the offer, and immediately tell your project sponsor so they're aware of what you're doing. D. Thank the vendor but decline the offer because you've already made another arrangement for this vacation. Ask them if you can take a rain check and arrange another time to use the condo.
You are a project manager for Move It Now trucking company. Your company specializes in moving household goods across the city or across the country. Your project involves upgrading the nationwide computer network for the company. Your lead engineer has given you the following estimates for a critical path activity: 60 days most likely, 72 days pessimistic, 48 days optimistic. What is the standard deviation? A. 22 B. 20 C. 2 D. 4
What is the purpose of the project charter? A. To recognize and acknowledge the project sponsor B. To recognize and acknowledge the existence of the project and commit organizational resources to the project C. To acknowledge the existence of the project team, project manager, and project sponsor D. To describe the selection methods used to choose this project over its competitors
You are a project manager working for Mail House King. Your company processes orders for several mail-order catalog companies. Your project is to install new mail-sorting equipment and software. You’ve had some problems and experienced some variances so far during the project. Your project sponsor has asked for an EAC. You know the following information: PV = 800, BAC = 700, EV = 675, AC = 750, and ETC = 30. Which of the following is the correct EAC given the circumstances? A. 778 B. 780 C. 861 D. 833
Your project is in the Scope Definition process. You've just completed the WBS. Which of the following is true? A. The WBS breaks the project deliverables down to a level where alternatives identification can be used to determine how level two assignments should be made. B. The WBS breaks the project deliverables down to a level where project constraints and assumptions can be easily identified. C. The WBS breaks the project deliverables down to the work package level where product analysis can be documented. D. The WBS breaks the project deliverables down to the work package level where cost and time estimates can be easily determined and quality control measurements can be determined.