You are a project manager for a software manufacturing firm. The project you've just finished created a new software product that is expected to become a number-one seller. A friend of yours is a certified software instructor. They have asked you for a copy of the software prior to the beta release through the marketing department so they can get familiar with it. What is the most appropriate response?
A. Since your friend is certified to teach your company's brand of software, provide them with a copy of the software.
B. Ask them to sign a nondisclosure agreement before releasing a copy of the software.
C. Decline the request since you stand to gain from this transaction by receiving free training.
D. Decline the request because the software is the intellectual property of the company.
Answer / Mohd Shikoh
B. Ask them to sign a nondisclosure agreement before releasing a copy of the software.
| Is This Answer Correct ? | 0 Yes | 0 No |
What are the different software reengineering activities?
You are a project manager for an engineering company. Your company won the bid to add ramp-metering lights to several on-ramps along a stretch of highway at the south end of the city. You subcontracted a portion of the project to another company. The subcontractor's work involves digging the holes and setting the lamp poles in concrete. The subcontractor's performance is not meeting the contract requirements, because the poles are not buried to the correct depth. Which of the following is true? A. You are in the Quality Assurance process and have performed a quality audit to assure correctness of work. B. You are in the Scope Verification process and have performed a quality audit to assure correctness of work. C. You are in the Contract Administration process and have completed a contract audit to assure the subcontractor's performance meets the contract requirements. D. You are in the Performance Reporting process and have completed a performance review of the contractor's work.
You are developing your project schedule and have decided to use the PERT method to determine project duration. The estimates you've gathered so far include the following: Most likely is 200 hours, optimistic is 180 hours, and pessimistic is 220 hours. Which of the following is the correct PERT estimate? A. 190 B. 266 C. 200 D. 210
what kind of questions can be asked from SDLC for a project leader role?
If your expected value is ll0 and the standard deviation is l2, which of the following is true? A. There is approximately a 99 percent chance of completing this activity between 86 and 134 days. B. There is approximately a 68 percent chance of completing this activity between 98 and 122 days. C. There is approximately a 95 percent chance of completing this activity between 98 and 122 days. D. There is approximately a 75 percent chance of completing this activity between 86 and 134 days.
You are managing a project to install a new postage software system that will automatically print labels and administer postage for certified mailings, overnight packages, and other special mailing needs. You've attempted to gain the cooperation of the business analyst working on this project and need some answers. She is elusive and tells you that this project is not her top priority. To avoid situations like this in the future, you should: A. Establish the business analyst's duties well ahead of due dates and tell her you'll be reporting on her performance to her functional manager. B. Establish the business analyst's duties well ahead of due dates and tell her you are expecting her to meet these expectations because the customer is counting on the project meeting due dates to save significant costs on their annual mailings. C. Negotiate with the business analyst's functional manager during the planning process to establish expectations and request to participate in the business analyst's annual performance review. D. Negotiate with the business analyst's functional manager during the planning process to establish expectations and inform the functional manager of the requirements of the project. Agreement from the functional manager will assure the cooperation of the business analyst.
As a project manager, you're responsible for maintaining and ensuring integrity for all of the following except: A. Personal integrity of others B. Project management process C. Personal integrity D. Product integrity
You have just prepared an RFP for release. Your project involves a substantial amount of contract work detailed in the RFP. Your favorite vendor drops by and offers to give you and your spouse the use of their company condo for your upcoming vacation. It's located in a beautiful resort community that happens to be one of your favorite places to go for a get away. What is the most appropriate response? A. Thank the vendor but decline the offer, as you know this could be considered a conflict of interest. B. Thank the vendor and accept. This vendor is always offering you incentives like this, so this offer does not likely have anything to do with the recent RFP release. C. Thank the vendor, accept the offer, and immediately tell your project sponsor so they're aware of what you're doing. D. Thank the vendor but decline the offer because you've already made another arrangement for this vacation. Ask them if you can take a rain check and arrange another time to use the condo.
You are a contract project manager for a wholesale flower distribution company. Your project is to develop a website for the company that allows retailers to place their flower orders online. You will also provide a separate link for individual purchases that are ordered, packaged, and mailed to the consumer directly from the grower's site. This project involves coordinating the parent company, growers, and distributors. You are preparing a performance review and have the following measurements at hand: PV = 300; AC = 200; and EV = 250. What do you know about this project? A. The EAC is a positive number, which means the project will finish under budget. B. You do not have enough information to calculate CPI. C. The CV is a negative number in this case, which means you've spent less than what you planned as of the measurement date. D. The CV is a positive number in this case, which means you're under budget as of the measurement date.
A negative result from an SV calculation means which of the following? A. PV is higher than EV. B. PV equals one. C. EV is higher than PV. D. EV is higher than AC.
You are a project manager for Move It Now trucking company. Your company specializes in moving household goods across the city or across the country. Your project involves upgrading the nationwide computer network for the company. Your lead engineer has given you the following estimates for a critical path activity: 60 days most likely, 72 days pessimistic, 48 days optimistic. What is the standard deviation? A. 22 B. 20 C. 2 D. 4
The tools and techniques of Source Selection include all of the following except: A. Contract negotiation B. Work authorization system C. Weighting systems D. Independent estimates