Your project got delayed by 40 days and you have to keep it
back.what steps you would take.
Answers were Sorted based on User's Feedback
Answer / srk
Either
Identify those activities and execute them in parallel
or
add more resources to the project activities
or both
| Is This Answer Correct ? | 16 Yes | 0 No |
Answer / rajeev a
-Check those non critical activity which have some float, some of the resources from those activity can be put on critical actives.
-Try to see the activities which can be done in parallel.
-Check with customer if some low priority features can be postponed to further releases.
- Finally try to add some more resources which can be productive from day 1. Because in these kind of situation you will not have time to hand hold them.
| Is This Answer Correct ? | 3 Yes | 0 No |
Answer / s.thiru selvan
i have planing before how the project are prefectly complte
.and then runs to the my project.
| Is This Answer Correct ? | 2 Yes | 2 No |
Answer / a.barakat
first , we must start with critical activities ( most delay activities) and recover it first.
| Is This Answer Correct ? | 1 Yes | 1 No |
You are a project manager for a new software development project. You have a few activities that require specialized testing. The testing might need to be repeated more than once. Which of the following do you choose? A. The Graphical Evaluation and Review Technique because it allows for conditional branching and looping for the testing activity B. The Critical Path Method because it allows for float time to be calculated for the testing activity C. The Program Evaluation and Review Technique because it allows for conditional branching and looping for the testing activity D. The Program Evaluation and Review Technique because it allows for a weighted average distribution, which will even out the time needed for the testing activity
You are a project manager working on a new software product. Your company plans to market to businesses. The project sponsor told you that the project must be completed by September 1. The company plans to demo the new software product at a trade show in late September and therefore needs the project completed in time for the trade show. However, the sponsor has also told you that the budget is fixed at $85,000 and cannot be increased by even $10 due to overall budget cuts this year. You must complete the project within the given time frame and budget. Which of the following is the primary constraint for this project? A. Budget B. Quality C. Time D. Schedule
Describe function-oriented metrics.
What limits the options of the project team? A. Technology B. Constraints C. Deliverables D. Assumptions
You are implementing a sap project. implementation compled and development started and at that time you found that there is major problem with the system .It would take again time and customer is not happy with that ,in that case how do you convince customer?
How a project is made and deliverd to client? please put all detailed steps internally?
How do you communicate bad news in your team?
You are the project manager for a software consulting firm that is working on developing a new software program for a customer in another country. Things seem to be progressing well. Recently, your stakeholders examined the work of the project and formally accepted the work results. Which process was just performed? A. Scope Verification B. Quality Assurance C. Performance Reporting D. Quality Control
The tools and techniques of the Source Selection process include all of the following except: A. Contract negotiation B. Correspondence C. Independent estimates D. Screening system
You are the project manger for Xylophone Phonics. They produce children's software programs that teach basic reading and math skills. You are ready to assign project roles, responsibilities, and reporting relationships. Which project Planning process are you working on? A. Resource Planning B. Organizational Planning C. Staff Acquisition D. Human Resource Acquisition
The amount of authority a project manager possesses can be related to: A. The project manager’s communication skills B. The organizational structure C. The amount of authority the manager of the project manager possesses D. The project manager's influencing skills
You are a project manager for Laurel’s theater productions. Your new project is coming in over budget and requires a cost change through the cost change control system. The cost variance was projected using which of the following tools and techniques? A. Performance measurements B. Cost baseline measurements C. Computerized tools D. Performance reports