Your project got delayed by 40 days and you have to keep it
back.what steps you would take.
Answers were Sorted based on User's Feedback
Answer / srk
Either
Identify those activities and execute them in parallel
or
add more resources to the project activities
or both
| Is This Answer Correct ? | 16 Yes | 0 No |
Answer / rajeev a
-Check those non critical activity which have some float, some of the resources from those activity can be put on critical actives.
-Try to see the activities which can be done in parallel.
-Check with customer if some low priority features can be postponed to further releases.
- Finally try to add some more resources which can be productive from day 1. Because in these kind of situation you will not have time to hand hold them.
| Is This Answer Correct ? | 3 Yes | 0 No |
Answer / s.thiru selvan
i have planing before how the project are prefectly complte
.and then runs to the my project.
| Is This Answer Correct ? | 2 Yes | 2 No |
Answer / a.barakat
first , we must start with critical activities ( most delay activities) and recover it first.
| Is This Answer Correct ? | 1 Yes | 1 No |
You are a project manager for a new software development project. You have a few activities that require specialized testing. The testing might need to be repeated more than once. Which of the following do you choose? A. The Graphical Evaluation and Review Technique because it allows for conditional branching and looping for the testing activity B. The Critical Path Method because it allows for float time to be calculated for the testing activity C. The Program Evaluation and Review Technique because it allows for conditional branching and looping for the testing activity D. The Program Evaluation and Review Technique because it allows for a weighted average distribution, which will even out the time needed for the testing activity
You are the project manager for a new website for the local zoo. You need to perform Quantitative Risk Analysis. You'll use all of the following tools and techniques to accomplish this except: A. Data precision ranking B. Sensitivity analysis C. Decision tree analysis D. Interviewing
Sally is a project manager working on the Resource Planning process. She should consider all of the following when developing the resource requirements output except: A. WBS B. Supply purchase policies C. Resource rates D. Special knowledge and talents
Why do you want to switch over from IT to management?
You are the project manager for a cable service provider. Your project team is researching a new service offering. They have been working together for quite some time and are in the performing stage of Team Development. This stage of Team Development is similar to which of the following? A. Smoothing B. Achievement theory C. Hygiene theory D. Self-actualization
What do you mean by business object,condition object and costomising object?
You are a project manager for Pizza Direct, which is a retail pizza delivery store. Your company is competing with another retail store for the option of opening two new stores in a foreign country. You've been told that it is culturally unacceptable to eat certain foods in this country. You know that one of these foods happens to be a secret ingredient in the pizza sauce. What is the most appropriate response? A. Inform the potential partners that your sauce recipe is secret, but you’re certain there are no forbidden ingredients in it. B. Inform the potential partners that you suspect there might be a forbidden ingredient in the sauce and you'll request an investigation to determine if any of them exist in the sauce. C. Inform the potential partners that a forbidden ingredient exists in the sauce and determine to work with them to come up with another ingredient to replace that one. D. Don't tell the potential partners about the ingredient because the sauce they'll be using in the stores is shipped to them already prepared in cans. They won't know the ingredient is in the sauce.
What is the name of the unplanned response used to deal with negative risk events in the Risk Monitoring and Control process? A. Mitigation B. Contingency plans C. Workarounds D. Corrective action
You are a project manager for Snow Fun, a chain of retail shops specializing in winter spurts gear and clothing. You've been working on contract with Snow Fun and are ready to move on to your next assignment. As the project manager, you know all of the following are true regarding the project Closing processes except: A. Administrative Closure is always required at the close of the project. B. The Closing processes are the most often skipped processes. C. Administrative Closure should occur prior to Contract Closeout. D. Both Closing processes verify that the work and product of the project were completed satisfactorily.
You are the project manager for Heartthrobs by the Numbers Dating Services. You're working on an updated Internet site that will display pictures as well as short bios of prospective heartbreakers. You've just completed your project staff assignments and published the project team directory. Which process are you in? A. Resource Planning B. Organizational Planning C. Project Development Planning D. Staff Acquisition
Brainstorming and the Delphi technique are two types of information-gathering techniques found in which process? A. Risk Management Planning B. Risk Response Control C. Risk Identification D. Quantitative Risk Analysis
You have collected the performance measurement documentation for your project to be included in the project archives. What is the purpose of the performance measurement documentation? A. It's used as part of the formal acceptance process to verify contract expenditures. B. It's reviewed to make certain the project goals and objectives were met. C. It's included in the project archive documentation after confirming the accuracy of the measurements. D. It’s used as historical information for future project that are similar in scope to this project.