Your project got delayed by 40 days and you have to keep it
back.what steps you would take.
Answers were Sorted based on User's Feedback
Answer / srk
Either
Identify those activities and execute them in parallel
or
add more resources to the project activities
or both
Is This Answer Correct ? | 16 Yes | 0 No |
Answer / rajeev a
-Check those non critical activity which have some float, some of the resources from those activity can be put on critical actives.
-Try to see the activities which can be done in parallel.
-Check with customer if some low priority features can be postponed to further releases.
- Finally try to add some more resources which can be productive from day 1. Because in these kind of situation you will not have time to hand hold them.
Is This Answer Correct ? | 3 Yes | 0 No |
Answer / s.thiru selvan
i have planing before how the project are prefectly complte
.and then runs to the my project.
Is This Answer Correct ? | 2 Yes | 2 No |
Answer / a.barakat
first , we must start with critical activities ( most delay activities) and recover it first.
Is This Answer Correct ? | 1 Yes | 1 No |
All of the following are true regarding parametric modeling except: A. It's a form of top-down estimating. B. It's a mathematical model. C. It's a tool used to estimate project costs. D. It's a tool used to estimate project time.
You are a project manager for Cashiers Systems. Your company produces cashiering systems and software for the retail industry. Your customer has requested a change that will change the characteristics of the cashiering system. You've described the characteristics of the cashiering system using this tool and technique of the Integrated Change Control process: A. Product description B. Product analysis C. Decomposition D. Configuration management
Which of the following tools and techniques shows the impacts of one decision over another as well as the probability and cost of each risk along a logical path? A. Simulation B. Decision tree C. Probability/impact risk matrix D. Sensitivity analysis
What is one of the advantages of a functional structure? A. All employees report to one manager and have a clear chain of command. B. All employees report to two or more managers, but project team members show loyalty to functional managers. C. The organization is focused on projects and project work. D. Teams are collocated.
What are the 10 knowledge areas of project management?
What is tracing process? How this can be enabled?
As a PMP, one of your responsibilities is to ensure integrity on the project. When your personal interests are put above the interests of the project or when you use your influence to cause others to make decisions in your favor without regard for the project outcome, this is considered: A. Conflict of interest B. Using professional knowledge inappropriately C. Culturally unacceptable D. Personal conflict issue
Deliverables can be described as: A. The purpose for undertaking the project B. The verifiable results of products or services that must be produced to consider the project complete C. The specifications regarding the goals of the project that must be produced to consider the project complete D. The measurable outcomes of the project goals
You are a project manager for Cinema Snicker Productions. Your company specializes in producing comedy films for the big screen. Your latest project has just been canceled due to budget cuts. Which of the following is true? A. This project ended due to starvation because the funding was cut off B. This project ended due to integration because the resources were distributed elsewhere C. This project ended due to starvation because the resources were distributed elsewhere D. This project ended due to integration because the funding was cut off
Your project is in the Scope Definition process. You've just completed the WBS. Which of the following is true? A. The WBS breaks the project deliverables down to a level where alternatives identification can be used to determine how level two assignments should be made. B. The WBS breaks the project deliverables down to a level where project constraints and assumptions can be easily identified. C. The WBS breaks the project deliverables down to the work package level where product analysis can be documented. D. The WBS breaks the project deliverables down to the work package level where cost and time estimates can be easily determined and quality control measurements can be determined.
What are the tools and techniques of the Contract Administration process? A. Contract change control system, payment system, payment requests B. Contract change control system, contract negotiations, payment system C. Contract change control system, contract negotiations, contract changes D. Contract change control system, performance reporting, payment system
Which of the following processes serve as inputs to each other? A. Executing and Controlling B. Planning and Executing C. Planning and Controlling D. Executing and Initiation