Your project got delayed by 40 days and you have to keep it
back.what steps you would take.

Answers were Sorted based on User's Feedback



Your project got delayed by 40 days and you have to keep it back.what steps you would take...

Answer / srk

Either
Identify those activities and execute them in parallel
or
add more resources to the project activities
or both

Is This Answer Correct ?    16 Yes 0 No

Your project got delayed by 40 days and you have to keep it back.what steps you would take...

Answer / rajeev a

-Check those non critical activity which have some float, some of the resources from those activity can be put on critical actives.
-Try to see the activities which can be done in parallel.
-Check with customer if some low priority features can be postponed to further releases.
- Finally try to add some more resources which can be productive from day 1. Because in these kind of situation you will not have time to hand hold them.

Is This Answer Correct ?    3 Yes 0 No

Your project got delayed by 40 days and you have to keep it back.what steps you would take...

Answer / s.thiru selvan

i have planing before how the project are prefectly complte
.and then runs to the my project.

Is This Answer Correct ?    2 Yes 2 No

Your project got delayed by 40 days and you have to keep it back.what steps you would take...

Answer / a.barakat

first , we must start with critical activities ( most delay activities) and recover it first.

Is This Answer Correct ?    1 Yes 1 No

Post New Answer

More Project Management Interview Questions

Your project was just completed. Due to some unfortunate circumstances, the project was delayed causing cost overruns at the end of the project. This information might be useful on future projects in all of the following activities except: A. Cost estimating B. Allocating resources C. Product verification D. Activity estimating

1 Answers  


Your organization regularly uses a tool and technique of the Contract Closeout process to identify lessons learned, including the successes and failures, which will benefit future activity on this project and on future projects. Which tool and technique arc they using? A. Product documentation inspection B. Contract process review C. Performance measurement review D. Procurement audit

1 Answers  


What is one of the problems with project management software? A. The project manager manages the software instead of the project B. Project duration calculations are sometimes approximate. C. You cannot override the project management software decisions regarding schedules. D. It’s expensive and difficult to use.

1 Answers  


What is the process in the Executing process group that determines if the project satisfies quality怀standards, identifies lessons learned, and review quality management activities to verify the correct quality elements are being examined? A. Quality Control B. Quality Monitoring and Control C. Quality Assurance D. Scope Verification

1 Answers  


You are a fabulous project manager, and your team thinks highly of you. You are well respected by the stakeholders, management ream, and project team. When you make decisions, others follow your lead as a result of which of the following? A. Referent power B. Expert power C. Legitimate power D. Punishment power

1 Answers  


You are a project manager for Capella Systems. Your company writes custom software for accounting and financial systems for medium- to large-sized corporations. Your recent project has experienced some setbacks, and you've been forced to rework the design of one of the programs because it doesn't match the customer's requirements. Since some parts of the program have already been written, it will have to be rewritten so that it matches the design changes. This rework has increased costs, and you're beginning to notice some signs of poor morale because of the rework. Which of the following is true? A. The problems occurred because the WBS was not constructed properly. B. The quality assurance plan was carried out correctly, which is how the design problems were discovered. C. The problems occurred as a result of poor scope definition. D. The Risk Management Planning process details these kinds of risks and the responses you should put into place should they occur.

1 Answers  


You are a project manager for a network cabling project for your organization. Your project team is made up of six full-time employees and three contractors. This is the first time they have all worked together. This project requires accurate information exchange at all times during the life of the project. How many lines of communication exist among the project team members? A.36 B.41 C.18 D.34

1 Answers  


What are the skills required to be a project manager? Followup question, Rate yourself in each of the skill with examples.

18 Answers   Cognizant, Microsoft,


How do you handle change request?

1 Answers  


How to deal with underperforming team members?

1 Answers  


What are the qualities of a good project manager?

1 Answers  


What do you think you can bring to this position?

1 Answers   Ross Stores, Starbucks,


Categories