You have just prepared an RFP for release. Your project involves a substantial amount of contract work detailed in the RFP. Your favorite vendor drops by and offers to give you and your spouse the use of their company condo for your upcoming vacation. It's located in a beautiful resort community that happens to be one of your favorite places to go for a get away. What is the most appropriate response?
A. Thank the vendor but decline the offer, as you know this could be considered a conflict of interest.
B. Thank the vendor and accept. This vendor is always offering you incentives like this, so this offer does not likely have anything to do with the recent RFP release.
C. Thank the vendor, accept the offer, and immediately tell your project sponsor so they're aware of what you're doing.
D. Thank the vendor but decline the offer because you've already made another arrangement for this vacation. Ask them if you can take a rain check and arrange another time to use the condo.
No Answer is Posted For this Question
Be the First to Post Answer
Change control system, configuration management, performance measurement, additional planning, and project management information system are tools and techniques of which process? A. Integrated Change Control B. Scope Change Control C. Schedule change control D. Cost change control
All of the following are tools and techniques of the Schedule Development process except? A. CPM B. RAM C. GERT D. PERT
You are a project manager for a telecommunications firm. You're working on a project that entails upgrading technical hardware and equipment. The estimated cost of the hardware and equipment is $1,725,000. You are reviewing products from three different vendors. One of the vendors offers you and your family the use of the company yacht for the upcoming three-day weekend. What is the most appropriate response? A. Thank them and accept. You don't believe there is a conflict of interest or an integrity issue at stake. B. Thank them and decline. You know this could be considered personal gain, which could call your integrity into question. C. Thank them and accept. Immediately report your actions to the project sponsor so that your motives are not called into question after the fact. D. Thank them and decline. You know this could be considered an integrity issue on the part of the vendor.
The primary function of the Closing process is to: A. Formalize lessons learned and distribute this information to project participants B. Perform audits to verify the project results against the project requirements C. Formalize project completion and disseminate this information to project participants D. Perform post-implementation audits to document project successes and failures
What are the outputs of the Team Development process? A. Performance improvements, input to performance appraisals B. Input to performance appraisals, reward and recognition systems C. Performance improvements, input to performance appraisals, performance reports D. Work results, input to performance appraisals, performance reports
You are the project manager for a software consulting firm that is working on developing a new software program for a customer in another country. Things seem to be progressing well. Recently, your stakeholders examined the work of the project and formally accepted the work results. Which process was just performed? A. Scope Verification B. Quality Assurance C. Performance Reporting D. Quality Control
What do you think you can bring to this position?
0 Answers Ross Stores, Starbucks,
Your project was just completed. Due to some unfortunate circumstances, the project was delayed causing cost overruns at the end of the project. This information might be useful on future projects in all of the following activities except: A. Cost estimating B. Allocating resources C. Product verification D. Activity estimating
Your project was just completed, accepted, and closed. As is customary for your organization, you conduct a post-implementation audit. The purpose of this audit includes all of the following except: A. Evaluating project goals and comparing them to project product B. Reviewing successes and failures C. Documenting the acceptance of the work results D. Documenting possible improvements for future projects
You are a project manager for Dutch Harbor Consulting. Your latest project involved the upgrade of an organization’s operating system on 236 servers. You performed this project under contract. You are in the Closing process and know that product verification is for what purpose? A. To verify the goals of the project and assure the product of the project is complete B. To evaluate all the work of the project and compare results to project scope C. To verify all the work was completed correctly and satisfactorily D. To evaluate project goals and assure the product of the project meets the requirements
Which of the following is constraint chat you might find during the Organizational Planning process? A. Organizational structure, expected staff assignments, collective bargaining agreements, and project management team preferences B. Organizational structure, organizational interfaces, technical interfaces, and interpersonal interfaces C. Organizational interfaces, expected staff assignments, collective bargaining agreements, and project management team preferences D. Organizational interfaces, technical interfaces, and interpersonal interfaces
Your project depends on a key deliverable from a vendor you've used several times before with great success. You're counting on the delivery to arrive on June 1. This is an example of : A. Constraint B. Objective C. Assumption D. Goal