Answer / ajai kumar
Entry Criteria
1. Testing Environment is available and accessible by QA team
2. Confirm QA Access to Bug Tracking System
3. QA is provided with baselined Specifications for
respective features.
4 QA is provided with documentation which defines the
technical details of each feature, like feature scope,
validations, etc.
5. Test plan document and Test cases has to be signed off by
Project Lead
6. Unit and Integration tests were executed and passed.
7. Bugs that are fixed are moved to QA state for regression
(for consecutive iterations / builds)
Exit Criteria:-
1. All tests have been executed and passed, or approval
obtained from the Cross Functional Team (CFT) for all
unexecuted or failed tests. All defect fixes have been
verified and moved to appropriate state
2. All High Priority/Critical defects have been addressed
appropriately.
3. All Major and average priority defects have an adequate
documented work-around agreed upon by the CFT.
4. Test Execution Report has been written and submitted for
approval.
| Is This Answer Correct ? | 4 Yes | 0 No |
Answer / mfsi_satyakamm
Entry Criteria is like a set of conditions which when
satisfied enters a testing process or starts executing a test.
e.g.- say first page of the document itself contains many
faults, so we can't proceed further unless the faults are
reduced because it has no meaning if we proceed further with
such a number of faults in the first page itself.
Exit Criteria is like a set of conditions which when
satisfied exits a testing process or stops executing a test.
If certain conditions satisfies then the test is passed i.e.
test is successful and it fulfills the exit criteria.
| Is This Answer Correct ? | 3 Yes | 0 No |
there are many test cases in our test case repository like function,integration,system,acceptance test case so which test case should test engineer test first.? please answer me . thanks
1.How to maintain the Bug status Report? 2.What is project based Company and product based company?
What is defect leaking and defect release
I would like to know about the steps to follow for testing a .NET web application. Please provide detailed steps with more general scenarios.
What is the use of RTM?
what we do when our reported defect reject?
What is the difference between defect tracking tool and QC?
Hi friends, Is there any difference in testing the web applications which are built on different technologies like .NET,PHP,J2ee etc ?if yes then how the testing differes from one to other?(for me its urgent to know the diff. btn .net and php).can anybody answer soon....!
What is a Recovery Testing
What all document are required to testing?
What is the Database testing?? Is it necessary to have database knowledge for testing?had you ever tested the software by entering input at the front end and check it at back end?
Condition testing is a control structure testing technique where the criteria used to design test cases is that they Option 1 Rely on basis path testing Option 2 Exercise the logical conditions in a program module Option 3 Select test paths based on the locations and uses of variables Option 4 Focus on testing the validity of loop constructs