What is change management?
Answer / umavijay
Change management is also called as change request.
1. prepare change request
2. Perform impact analysis (work product, effort schedule)
3. Re-estimate delivery schedule
4. Review impact with senior management and other effected
groups, as necessary
5. Obtain approval from change control board
6. Implement the approved changes in the work item
7. Perform review/testing process to verify the
implementation of change
8. Update closure status of change request.
| Is This Answer Correct ? | 4 Yes | 0 No |
What is Recovery Testing?
In an example of a Bank Teller requesting that her computer program should include an addition that shows the full Customer Profile on her main screen, what would a Waterfall vs. Agile approach include and/or look like for such a request?
what is the strength of present company
what is Test senario?
what is Desk Checking?
What is the difference between GUI and UI testing?
What do you think is a good investment, a defect tracking system or a test management system integrated with a defect tracking tool? Please comment.
What should your qa documents include?
What is capture/replay tool?
What is the strategy for automation test plan?
Any quality test-tracking tool which has live & automated dashboards so that the entire team is updated at any given point of time?
If we don't caught any bug in all build, then what we can say - 1. Bad Coverage 2. Excellent Coding 3. Bad Testing